| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/01/2018 | FRAMING | Approved | UNIT 2 COMPLETE | |
| 05/30/2018 | FRAMING | Partial Approval | UNIT # 4 APPROVED. TRUSS FIX APPROVED. SUPPLY BLOCKING UN UNIT #2. |
|
| 05/02/2018 | FRAMING | Partial Approval | ALL UNITS EXCEPT FOR NUMBER 2 & 4 BATHROOM LIDS. ENGINEERING REPAIR REQUIRED. | |
| 04/27/2018 | FRAMING | Not ready for Inspection | INCORRECT TRUSS DRAWINGS | |
| 04/26/2018 | FRAMING | Denied | ROOF TRUSSES HAVE BEEN CUT/ MODIFIED, RE-INSPECT ROOF TRUSSES ON ALL UNITS IN BUILDING #5. INCORRECT FIRE CAULK ON FIRE WALL IN BUILIDNG #5. RE INSPECT ALL FIRE WALLS IN BUILIDNG #5. HOLE IN FIREWALL IN UNIT #4. UNIT #4, DUCT IS NOT CONNECTED TO ANYTHING IN BATHROOM. SUPPORT VENTS ON THREE SIDES. |