Permit: T16CM08968

Parcel: 10712170F

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T16CM08968

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
09/13/2018 ENGINEERING - FINAL Approved
05/17/2018 ENGINEERING - FINAL Partial Approval BUILDING 2 HAS BEEN APPROVED FOR THE TCO. THE CONTRACTOR MUST MAINTAIN THE SEPERATION OF ALL CONSTRUCTION OPERATIONS AND THE GENERAL PUBLIC. THIS WILL ALSO INCLUDE THE PARKING OF PRIVATE AND CONSTRUCTION VEHICLES OUTSIDE OF THE AREA ALLOWED FOR THE GENERAL PUBLIC.
05/16/2018 ENGINEERING - FINAL Denied PROVIDE A CLEAN 24 FOOT PAAL/ROADWAY AND A 6 FOOT FENCE FOR THE SEPARATION OF THE GENERAL PUBLIC AND THE CONSTRUCTION AS PREVIOUSLY DISCUSSED ON 5/14/18. THIS AREA WILL NEED TO STAY FREE AND CLEAR OF ALL CONTRUCTION TRAFFIC AND AND VEHICLE PARKING.
05/16/2018 ENGINEERING - FINAL Denied THE TRENCHES HAVE BEEN BACKFILLED, THE DUMPSTER HAS BEEN REMOVED, AND THE FENCE HAS BEEN PLACED TO SEPERATE THE CONSTRUCTION FROM THE GENERAL PUBLIC. THE SITE WILL BE CHECKED IN THE MORNING TO VERIFY THAT ALL OF THE CONTRACTORS PERSONNEL ARE PARKING OUTSIDE OF THE PAAL.
05/15/2018 ENGINEERING - FINAL Denied COMPLETE CONSTRUCTION AND/OR SEPARATE REMAINING CONSTRUCTION FROM PUBLIC ACCESS
05/15/2018 ENGINEERING - FINAL Denied NO CHANGE IN THE AREA FROM YESTERDAY AFTERNOON, THEY STILL NEED TO HAVE THE DIRT REMOVED FROM THE SIDEWALKS, INSTALL THE BARRIER FENCE, REMOVE ALL CONSTRUCTION VEHICLES FROM WITHIN THE AREA.
05/14/2018 ENGINEERING - FINAL Denied JOHN ASKED ME COME TO THE SITE AND LOOK AT WHAT IT WILL TAKE FOR HIM TO GET A TCO FOR BUILDING 2. I MET WITH HIM ON SITE AND LOOKED OVER THE AREA ADJACENT TO THIS SITE. THEY HAVE STARTED CONSTRUCTION ON ANOTHER BUILDING ACROSS THE STREET FROM BUILDINGS 1 AND 2. THEY ARE CURRENTLY INSTALLING THE UNDER GROUND PIPE FOR THE BUILDING AND HAVE THE SPOIL MATERIAL LOADED ONTO THE ADJACENT SIDEWALK AND HAVE PUSHED THE BARRIER FENCE OUT INTO THE ROADWAY. I ADVISED JOHN THAT THEY WILL NEED TO REMOVE ALL OF THE SOIL FROM THE SIDEWALKS AND PLACE THEIR BARRIER FENCE BACK ONTO THE SIDEWALKS FOR SEPERATION OF TRAFFIC. I WILL NEED TO HAVE A 24 FOOT WIDE PAAL ADJACENT TO BUILDING 1 AND 2 BEFORE THEY CAN HAVE A TEMPORARY C OF O. ALSO IN THE PAAL ADJACENT TO THESE BUILDINGS THE CONSTRUCTION CREWS ARE PARKING AND THERE IS A CONSTRUCTION TRASH DUMPSTER THAT WILL NEED TO BE REMOVED. ONCE ALL OF THE AREA IS CLEARED THEY WILL HAVE TO PLACE A 6 FOOT BARRIER FENCE ALONG THE OUTSIDE OF THE PAAL SOUTH AND WEST OF BUILDINGS 1 AND 2 BEFORE I WILL CONSIDER THE RELEASE FOR THE TCO.