Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/09/2018 | MECHANICAL - FINAL | Approved | IVRS - Inspection :* | |
| 06/29/2018 | MECHANICAL - FINAL | Partial Approval | IVRS - Inspection :* TERMINATE CONDENSATE LINE |
|
| 06/29/2018 | MECHANICAL - FINAL | Partial Approval | PENDING BLOWER TEST CERT | |
| 05/17/2018 | MECHANICAL - FINAL | Denied | LOWER CLEAN OUTS TO GRADE OPEN BOXES THROUGHOUT STOOP REAR EXIT DOOR TERMINATE CONDENSATE LINE TO GROUND SECURE BATH VANITIES INSTALL ANTI TILT STOVE COMPLETE MASTER BATH AND LAUNDRY GARAGE SERVICE DOOR TO SELF CLOSE PROVIDE CERTS |
|
| 05/17/2018 | MECHANICAL - FINAL | Denied | LOWER CLEAN OUTS TO GRADE OPEN BOXES THROUGHOUT STOOP REAR EXIT DOOR TERMINATE CONDENSATE LINE TO GROUND SECURE BATH VANITIES INSTALL ANTI TILT STOVE COMPLETE MASTER BATH AND LAUNDRY GARAGE SERVICE DOOR TO SELF CLOSE PROVIDE CERTS |