Inspection History Details
Inspection Status: Approved
Inspection History: FIRE - FINAL
Permit Number - T16CM07685
Inspection Description - FIRE - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/21/2018 | FIRE - FINAL | Approved | ||
| 11/15/2018 | FIRE - FINAL | Partial Approval | Ok for TCO for the 6th floor | |
| 11/15/2018 | FIRE - FINAL | Partial Approval | 1) The new FACP that is capable and listed for smoke control still needs to be built. 2) Existing FACP needs to be de-energized and removed 3) New FACP needs to be installed. Just so that we are all clear on these issues...This may take a day or two to complete. Obviously they will be without an active fire alarm while this whole process is being completed. Because the panel is being replaced and a new program is being written and installed we will need to test the building fire alarm again for proper operation. Testing the fire alarm again will take about 2 days. Only after we test the fire alarm would they be allowed to come off fire watch. 4) The smoke detectors in the stairwells were removed by the recommendation of Jensen Hughes. These smoke detectors were required by TFD as a complete smoke system due to the Not a High Rise but a High Rise issue. They will need to be put back into service and tested. 5) The smoke detectors in the corridors by the stairwell need to be removed and hard-piped as a requirement from Jensen Hughes for the smoke control system 6) All water flow, tamper and fire ump wiring needs to be removed and hard-piped as a requirement from Jensen Hughes for the smoke control system 7) The Smoke Control Graphic Annunciator is still under review from Jensen Hughes and has not been approved nor has it been ordered yet. 8) Other required Graphic Annunciator has not been approved by TFD nor has it been ordered yet 9) TFD is still awaiting fire alarm plans (exclusive of smoke control) for approval prior to final testing and COFO. They have been working off the approved set from the beginning. The approved set does not show any of the hundred or so smoke detectors and the operation that we requested. 10) The 6th floor still needs to have the control modules and smoke detectors installed and tested 11) The roof needs to have the NAC (Notification appliance circuit) installed and notification devices terminated. 12) Need to order and install the roof duct detectors for the smoke control and the elevator shaft 13) Test the Bi-Directional Antenna and confirm the fire alarm signals 14) Confirm that the complete fire alarm system is on the generator back up (Only floors B-2 are the generator) 15) Confirm the two hour rated cable for the smoke control system has been installed 16) Need to install and verify the printer for the fire alarm Outstanding fire sprinkler items: 1) Need to perform the final walk of the 6th floor 2) Roof needs to have the fire sprinkler trimmed 3) Roof needs to have the fire sprinkler final performed 4) Standpipe on the roof needs to be painted 5) Standpipe on the roof needs to have the gauge installed 6) Standpipe North stair is now obstructed by smoke controls. Need to adjust the standpipe connection so that we can connect our house 7) Fire pump test header is missing the cap 8) All water flow, tamper and fire pump signals need to be re-confirmed to the FACP once they are hard piped Outstanding Building items: 1) Fire rated doors Jackson 2 hour corridor need to have the proper gaskets installed, the proper hard ware installed. As of right now the doors are installed but with the current open/closing hardware they cannot take the trash out of the building. In order to take the trash out they need to disconnect the hard ware. Hardware was unlatched when I was out. This is unacceptable. 2) The stairwells still need to have the illumination installed 3) Jensen Hughes has requested some lighting changes be made in the stairwell regarding the smoke control system 4) The south stairwell roof access needs to have the sign-age installed 5) Roof elevator and equipment room need to have proper sign-age installed 6) 6th floor needs to have the damper stickers installed 7) The elevator communication head end needs to be moved to the fire alarm control center room 8) Need to have the table in place in command room along with copies of the electrical, mechanical, fire sprinkler, smoke control drawings 9) Roof top needs to have the emergency and exit lights installed and on the back up generator 10) Smoke control needs to have the air-balance test scheduled and performed 11) Jensen Hughes needs to test the smoke control system. As of this morning Jensen Hughes as still not approved the fire alarm plans for the smoke control. |
|
| 11/01/2018 | FIRE - FINAL | Partial Approval | OF FOR TCO 5th Floor | |
| 10/30/2018 | FIRE - FINAL | Partial Approval | 5th floor, need to add the fire damper stickers. Lowe head room 501 closet by entry door | |
| 10/04/2018 | FIRE - FINAL | Partial Approval | Ok to occupy the 4th floor | |
| 09/06/2018 | FIRE - FINAL | Partial Approval | All fire alarm power supplies 3rd floor and up need to be on a dedicated circuit that is backed up by the generator The head with dry wall needs to be replaced room 307 and right outside that room in the hall way SW exit sign needs to be unmasked Change the stairwell signs so that they let contractors know they no longer can access that floor and let the other side know that they can OK for TCO to occupy the 3rd floor |
|
| 08/23/2018 | FIRE - FINAL | Partial Approval | Ok to occupy the basement, 1st and 2nd floor | |
| 08/20/2018 | FIRE - FINAL | Partial Approval | Make sure that all the doors are in place ie: FACP Room and fire pump room. Yes, you can use the non rated doors until your doors arrive Provide a Sensitivity report for all the smoke detectors. Replace/clean the dirty smoke detectors The FACP needs to be "trouble" free for CofO Provide us two key fobs for access for the KNOX Boxes Hang the Gas valve sign Fire pump test header needs to be installed. A-AAA stated that they ordered this like a month ago Provide documentation/ receipt showing that the new door hardware has been purchased Electrical room 6th floor needs to have a protective barrier in place. |
|
| 08/01/2018 | FIRE - FINAL | Partial Approval | 1)F.A.C.P. Room (need the door installed and the sign) 2) F.D.C. Standpipe Room (need door installed and the sign) 3) Need Fire Pump Test Header Sign 4) All Standpipe Rooms need to have a sign that reads (Standpipe Room) not Riser Room 5) Electrical Room 1st Floor missing sign 6)Replace the missing escuthcheon in the "time out" room 7) Dampers need to be installed. Access points for the Fire Dampers shall be permanently identified on the exterior by a label having letters not less than 0.5 inch in height reading "Fire Damper" IMC 2012 607.4 Access and Identification 8)Electrical rooms 5th and 6th floor need to have a protective barrier in place. Smoke detectors need to be protected from construction debris for the remainder of the project. 9) Stairwell permanent door hardware: IBC 2012 403.5.3 Stairway door operation. Stairway doors other than exit discharge doors, shall be permitted to be locked from the stairwell side. Stairwell doors that are locked from the stairwell side shall be capable of being unlocked simultaneously without unlatching upon a signal from the fire command center. 40.3.5.3.1 Stairway communication system. A telephone or other two-way communication system connected to an approved constantly attended location shall be provided at not less than every fifth floor in each stairwell where the doors to the stairway are locked.10) At a minimum show receipt that signage meeting the following requirements have been ordered. IBC 2012 1022.9 Stairway identification signs. A sign shall be provided at each floor landing in an interior exit stairway and ramp connecting more than three stories designating the floor level, the terminus of the top and bottom of the interior exit stairway and ramp and the identification of the stair or ramp. The signage shall also state the story of, and the direction to, the exit discharge and the availability of roof access from the interior exit stairway and ramp for the fire department. The sign shall be located 5 feet above the floor landing in a position that is readily visible when the doors are in the open and closed positions. In addition to the stairway identification sign, a floor-level sign in raised characters and braille complying with ICC A117.1 shall be located at each floor-level landing adjacent to the door leading from the interior exit stairway and ramp into the corridor to identify the floor level. •1022.9.1 Signage requirements. Stairway identification signs shall comply with all of the following requirements. ?The signs shall be a minimum size of 18 inches by 12 inches ?The letters designating the identification of the interior exit stairway and ramp shall be a minimum of 1.5 inches in height. ?The number designating the floor level shall be a minimum of 5 inches in height and located in the center of the sign ?All other lettering and numbers shall be a minimum of 1 inch in height. ?Characters and their backgrounds dhal have a non-glare finish. Characters shall contrast with their background, with either light characters on a dark background or dark characters on a light background. ?When signs are required by Section 1022.9 are installed in the interior exit stairway and ramps of buildings subject to Section 1024, the signs shall be made of the same materials as required by Section 1024.4 (1024 Luminous Egress Path Marking Fire opinion not ready for TCO due to items not being complete. TCO pending approval from BCO. |
|
| 07/25/2018 | FIRE - FINAL | Partial Approval | Per my inspection Tuesday, July 24th, 2018 the Tucson Fire Department is requesting that the following items be completed for the above mentioned project prior to a Temporary Certificate of Occupancy being issued for the Basement, 1st and 2nd floors. 1) Need to install proper fire signs (sign shall be red and white reflective minimum of 4" letters with a stroke width of ½"): a. F.D.C b. Fire Pump Test Header c. F.A.C.P. Room d. F.D.C. Standpipe Room e. Fire Pump Room f. Standpipe Room (on each floor on the south side of the building Standpipe location doors) g. All control valves need proper signage all floors h. Electrical Equipment Room i. Mechanical Equipment Room j. Gas Shut off Valve k. Other critical utilities need to be labeled as well 2) Bike room, Jackson, Broadway and Game room front entry doors need power and hardware 3) Properly enclose the trash chute at the lid 4) Lower 2 heads Jackson entry way 5) Replace the missing escutcheon in the "time out" room 6) Caulk, frame and sweep the north stair 1st floor door frame. 7) Fire sprinkler standpipe outlets need to be rotated facing outward for proper fire department connection to be made (all floors) 8) Replace the painted head in Room 207 closet 9) Replace the painted head in Room 206 bathroom 10) Access points for the Fire Dampers shall be permanently identified on the exterior by a label having letters not less than 0.5 inch in height reading "Fire Damper" IMC 2012 607.4 Access and Identification 11) Cable Closet 2nd Floor needs to have the ceiling properly sealed 12) Room 201 needs to have the skirt in the kitchen replaced 13) Room 203 needs to have the skirt in the kitchen replaced 14) Replace the painted head in Room 204 Front entry and closet 15) Replace painted head 2nd floor hallway by room 204 and the water closet 16) Replace the bent head 2nd floor outside of the water closet 17) Replace the missing fire extinguisher 2nd floor north stairwell 18) Replace the painted heads in the basement Approx. 7 19) 6th floor fire alarm notification devices need to be synchronized 20) Front lobby, game room and hall by basement stairwell needs to have emergency lighting installed 21) Electrical rooms floors 3-6 need to have a protective barrier in place. Smoke detectors need to be protected from construction dust and debris for the remainder of the project. 22) Stairwell permanent door hardware: IBC 2012 403.5.3 Stairway door operation. Stairway doors other than exit discharge doors, shall be permitted to be locked from the stairwell side. Stairwell doors that are locked from the stairwell side shall be capable of being unlocked simultaneously without unlatching upon a signal from the fire command center. 40.3.5.3.1 Stairway communication system. A telephone or other two-way communication system connected to an approved constantly attended location shall be provided at not less than every fifth floor in each stairwell where the doors to the stairway are locked. 23) At a minimum show receipt that signage meeting the following requirements have been ordered. IBC 2012 1022.9 Stairway identification signs. A sign shall be provided at each floor landing in an interior exit stairway and ramp connecting more than three stories designating the floor level, the terminus of the top and bottom of the interior exit stairway and ramp and the identification of the stair or ramp. The signage shall also state the story of, and the direction to, the exit discharge and the availability of roof access from the interior exit stairway and ramp for the fire department. The sign shall be located 5 feet above the floor landing in a position that is readily visible when the doors are in the open and closed positions. In addition to the stairway identification sign, a floor-level sign in raised characters and braille complying with ICC A117.1 shall be located at each floor-level landing adjacent to the door leading from the interior exit stairway and ramp into the corridor to identify the floor level. " 1022.9.1 Signage requirements. Stairway identification signs shall comply with all of the following requirements. o The signs shall be a minimum size of 18 inches by 12 inches o The letters designating the identification of the interior exit stairway and ramp shall be a minimum of 1.5 inches in height. o The number designating the floor level shall be a minimum of 5 inches in height and located in the center of the sign o All other lettering and numbers shall be a minimum of 1 inch in height. o Characters and their backgrounds dhal have a non-glare finish. Characters shall contrast with their background, with either light characters on a dark background or dark characters on a light background. o When signs are required by Section 1022.9 are installed in the interior exit stairway and ramps of buildings subject to Section 1024, the signs shall be made of the same materials as required by Section 1024.4 (1024 Luminous Egress Path Markings) 24) Separate access points for the contractors and public shall be maintained at all times 25) The south stairwell shall be allowed operable for contractors only and public in an emergency. To achieve this the door serving the 2nd floor shall be locked from the stairwell side. A sign shall be posted on the interior of this door "EMERGENCY EXIT ONLY" (sign shall be red and white reflective minimum of 4" letters with a stroke width of ½"). A sign shall be posted on the doors on stairwell side of the 3rd, 4th, 5th and 6th floor "CONTRACTORS ONLY" (sign shall be red and white reflective minimum 4" letter with a stroke width of 1/2") 26) Fire extinguishers shall be installed every 75 feet of travel on the construction floors 27) Fire alarm monitoring permit must be approved and obtained prior to fire alarm final |