Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T16CM07685
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 01/12/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | roof deck ok to pour | |
| 01/04/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 6th level ok | |
| 12/29/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | shear walls 3,4,5 ok, all columns except C.5/6 | |
| 12/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 6 north ok except shear walls and column C/2 | |
| 12/27/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | no work | |
| 12/22/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 6 deck ok | |
| 12/15/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 5 ok | |
| 12/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 12/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 12/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1st lift exterior walls ok | |
| 12/07/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 5 deck ok | |
| 11/29/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | no work | |
| 11/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 4th level shear walls 1,2,6 | |
| 11/24/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 11/22/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 11/21/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 4th level columns, shear walls 3,4,5 ok | |
| 11/20/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 4th level 7 columns ok | |
| 11/16/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 4 deck ok | |
| 11/03/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 3 SW 1,2,6 ok | |
| 11/02/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 3 columns ok shearwalls 3,4,5 ok |
|
| 11/01/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 3 ok | |
| 10/31/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LEVEL 3 COLUMNS 1.2/A.5,1/B,1/C,2/A.5,2/C,3/A.5,3/C,3/C.5, AND 4/C ONLY | |
| 10/26/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1005 LEVEL 3 DECK OK. | |
| 10/20/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 2 ok | |
| 10/19/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | no work | |
| 10/19/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2nd level shear walls 5,6 ok | |
| 10/17/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | level 2 columns ok | |
| 10/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2nd level deck ok to pour | |
| 10/04/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1st level shearwalls 1 and 2 ok | |
| 10/02/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1st level columns C.1/7 , C.1/8 , C.5/5 , C.5/6 , shearwall 6 |
|
| 09/29/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | shear walls 1st level-3, 4 ,5 , columns-A.5/7.8 , A.7/6 , A.7/7 , B.1/8 , C.1/5 , C.1/6 , C/4 , C.4/4 , C/3 , C.5/4 |
|
| 09/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | A.5/1.2 , A.5/2 , A.5/3 , B/1 , C/1 , C/2 , C/4 | |
| 09/25/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1st level deck ok pending engineer approval of clearence at vapor barrier | |
| 09/22/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 08/30/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | lower level perimeter and stair footers ok | |
| 08/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | lower level columns C/3 , C.1/6 , C.1/7 , C.1/8 ok | |
| 08/25/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | lower lever columns 3.6/B.2 , 4/C.1 , 5/C.1 , 3/C.4 , 4/C.4 , 5/C.4 , 8/B.1 , 7/A.7 . 7.8/A.5 , 6/A.7 , 5.5/A.5 lower level shear walls 1,2 |
|
| 08/24/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | lower level shear walls 3,4, 6 ok | |
| 08/22/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 08/21/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | lower level columns A.5/#.6 , A.5/3 , A.5/2 , A.5/1.2 , B/1 , C/1 , C/2 ok | |
| 08/18/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | lower level shear wall 5 ok | |
| 08/17/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 08/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | crane footer ok | |
| 08/11/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 08/10/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | elevator pit walls ok grade bem 5 ok bottom mat crane pad ok |
|
| 08/09/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | G.B.4 and 2 ok, shear wall 3 pending approval elevator pit floor ok, dowels at C/2 ok |
|
| 08/07/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 08/04/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 08/02/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | grade beams 1,2,3, ok caisson C.1/8 ok |
|
| 08/01/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | grade beam 4 east caisson ok | |
| 07/31/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 07/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | dweling at bottom level C.1/6 ok | |
| 07/27/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1st level caisson south caisson of grade beam 2 ok dowels at C.1/5 , C.1/6 ok |
|
| 07/26/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 07/24/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | caisson C.4/6 ok | |
| 07/21/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | caissons- C.4/1 , C.1/6 , C.1/5 , west end grade beam 4 , west endgrade beam 3 ok | |
| 07/20/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | caissons-east caisson grade beam 3 , C.1/8 , C/4 ok cages-(2) grade beam 4 , (1) grade beam 3 ok |
|
| 07/19/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | cassons- grade beam 5, C.4/5 , C.4/4 ok | |
| 07/18/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 07/17/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled | |
| 07/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | cages- C.5/6 , C/6 , C/7 , C.5/7 , C.4/5 , C/5 ok caissons- A.5/3.6 , B.2/3.6 , C.4/3 , grade beam 1 (2 caissons) ok |
|
| 07/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | cages-A.5/5 , A.5/4 , B/5 , B/2 , C/4 , A.5/3.6 , B/4 ok caissons-A.5/5.5 , A.7/6 , A.7/7 , A.5/7.8 , B.1/8 ok |
|
| 07/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | cages A.7/6 , C/8 , A.5/7.8 , A.5/5.5 , B/8 , A.7/7 , C.4/3 ok caissons A/3 , C/3 , A.5/2 , A.5/1.2 , B/1 , C/1 ok |
|
| 07/11/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | cages 3/A, 3/C, A.5/2, A.5/1.2, B/1, C/1, C.5/1.2, ok | |
| 06/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ok three footers at elevator pit east side | |
| 06/07/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancelled |