Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/09/2017 | ENGINEERING - FINAL | Approved | ||
| 08/24/2017 | ENGINEERING - FINAL | Denied | 1) DUE TO THE FACT THAT NO SITE/GRADING/LANDSCAPING OR STORM WATER INSPECTIONS WERE CALLED IN DURING CONSTRUCTION - PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT SITE/GRADING WAS IN CONFORMANCE WITH THE APPROVED GRADING PLAN. 2) PROVIDE SHORT TERM BIKE PARKING PER PLAN. 3) PROVIDE EXTRUDED CURB PER NOTE#24, PAGE C1.0 4) PROVIDE PARKING BUMPERS PER NOTE#28, PG C1.0 5) PROVIDE LOADING ZONE PER NOTE#21, PG C1.0 6) PROVIDE LONG TERM BIKE PARKING PER NOTE#37, PG C1.0 7) PROVIDE SET BACK FOR PARKING ALONG NORTH WALL PER NOTE#4, PG C1.0 8) APPROVED PLANS DO NOT SHOW A VALLEY GUTTER, BUT SHOW A DETAIL FOR ONE. |
|
| 08/03/2017 | ENGINEERING - FINAL | Denied | 1) NO CONTACT, NO ACCESS. 2) NO SITE INSPECTIONS CALLED IN THROUGHOUT CONSTRUCTION. 3) FINAL PERMIT # DP16-0171 |