Permit: T16CM07352

Parcel: 12310001A


Addresses:

1501 N CAMPBELL AV

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
04/23/2018 BUILDING - PROGRESS Approved
11/15/2017 BUILDING - PROGRESS Partial Approval SHEETROCK NAILING AND FIRE CAULKING: LEVEL #2, NORTH SHAFT - OK TO INSULATE AND SHEETROCK.
11/09/2017 BUILDING - PROGRESS Partial Approval FRAMING, CONTROL ROOM CEILING. OK TO SHEETROCK WHEN LIGHTING IS IN PLACE.
11/07/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT, NEW DOOR AREA (WEST SIDE) LOCATION; REBAR IS IN PLACE; OK TO PLACE GROUT.
11/06/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT - PARTIAL - GAS AREA CMU WALLS AT 20". OK TO GROUT ALL AREAS EXCEPT WEST WALL WHERE DOOR IS TO BE RELOCATED. WILL RECALL WHEN DOOR IS RELOCATED.
11/01/2017 BUILDING - PROGRESS Partial Approval FRAMING, LEVEL #3, ROOF FRAMING FOR EXHAUST SHAFTS - OK TO COVER PROGRESS AREAS. FRAMING AT LEVEL #1, (CEILINGS); ROOMS #10, 11, 12, 17. OK TO COVER CEILINGS.
10/26/2017 BUILDING - PROGRESS Partial Approval FRAMING - OFFICES AND BATHROOM (HARD LID CEILINGS). LEVEL #1, OK TO COVER CEILINGS..

ELECTRIC INTERMEDIATE: ELECTRIC IN WALLS OF CONTROL ROOM. OK TO COVER WALLS.

SHEETROCK NAILING: LEVEL #1 - CONTROL ROOM WALLS. LEVEL #2, WALLS AT GL: 1/B - C; C/2 - 4 (BOTH SIDES); SOUTH EASTCORNER OF BUILDING. OK TO TAPE PROGRESS AAREAS.
10/23/2017 BUILDING - PROGRESS Partial Approval ELECTRIC PROGRESS, ELECTRIC ABOVE CEILING AT LEVEL #1; CONDUITS, J-BOXES, FIRE ALARM BOXES.
10/17/2017 BUILDING - PROGRESS Cancelled IVRS - AP canceled
10/16/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: 6" STEM WALL FOR EQUIPMENT PAD AT GL: A.5/4 - 5. OK TO GROUT PROGRESS AREA.
10/06/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT - REBAR: FOOTINGS AT NORTH WEST STAIRS; FOOTING AT SOUTH EAST GAS METERING AREA. OK TO PLACE CONCRETE.

ELECTRIC INTERMEDIATE - LEVEL #1; MOTOR/VFD TERMINATIONS: HWP -1, 2, 3; CHILLED WATER PUMPS/VFD, #1, 2, 3.
10/04/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 9' 4", TOP-OUT: GL: F.5/1 - 3; 3/F - F.5. GROUTED.
09/29/2017 BUILDING - PROGRESS Partial Approval ELECTRIC INTERMEDIATE: MEDIUM VOLTAGE LINES (2 AT 6" CONDUITS- WIRES PULLED TO PULL BOX) LEVEL #2.
09/28/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: SCREEN WALL AT 48" AFFE. GL: 1 - 3/F -G. GROUTED
09/27/2017 BUILDING - PROGRESS Partial Approval ELECTRIC UNDERGROUND: 2 CONDUITS: 3/4" - 1" ATSOUTH EAST CORNER OF BUILDING (APPROXIMATELY 25'). OK TO COVER PROGRESS AREA.

ELECTRIC INTERMEDIATE - NORTH WEST RESTROOM - IN WALLS. OK TO COVER WALLS.
09/26/2017 BUILDING - PROGRESS Partial Approval ELECTRIC INTERMEDIATE: LEVEL #1, ROOMS AT GL: B/1, C/1.

ELECTRIC UNDERGROUND: NOT READY FOR INSPECTION. SOUTH WALL (SOUTH EASH CORNER) CONDUIT NOT IN TRENCHES.
09/22/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: SCREEN WALL FOOTINGS AT GL: .5/A - D; 1/F - G; 3/F - G; G/1 - 3. EAST SIDE 4 PEDISTAL FOOTINGS - POURED.

PLUMBING INTERMEDIATE: 4" GAS LINE FROM REGULATORS TO BUILDING - OK TO COVER.
09/21/2017 BUILDING - PROGRESS Partial Approval PLUMBING UNDERGROUND: 1 1/2" COPPER LINE FOR HAZ-MAT EYE WASH STATION: GL: .5A/4 - 5, 5/.5A - A. OK TO COVER.

MASONRY PRE-GROUT: CMU WALLS TOPPED-OUT AT 8'; GL: .5A/1 -5; 5/.5A - A; 1/.5A - A. OK TO GROUT AND CAP CMU WALLS.

FRAMING: EXTERIOR FRAMING AT GL: 5/E.75 - F, LEVELS #1 AND #2. OK TO COVER WALLS.

ELECTRIC UNDERGROUND; 4 EACH 1" CONDUITS AT GL: .5A/4 - 5; 5/.5A - A. OK TO COVER.

SHEETROCK NAILING: LEVEL #2, SINGLE LAYER APPLIED AT GL: C/3 - 4; A/2 - 3. OK TO TAPE PROGRESS AREAS.
09/20/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: EASTSIDE COLUMN FOOTINGS (3) AT GL: 5/D - F. *POURED AT TIME OF INSPECTION.
09/19/2017 BUILDING - PROGRESS Approved MASONRY PRE-GROUT, SCREEN WALL AT 0" - 48"; GL: .5A/1 - 5; 1/.5A - A; 5/A - .5A. OK TO GROUT PROGRESS AREA.
09/15/2017 BUILDING - PROGRESS Partial Approval FAMING AT ROOF LEVEL - SOUTH, EAST, WEST EXTERIOR WALLS. OK TO COVER PROGRESS AREAS.
09/13/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: STEM WALL/RETAINING WALL; COLUMN FOOTINGS AT GL: .5A/1 - 3; 1/.5A - A. OK TO PLACE CONCRETE.
09/12/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: LEVEL #1, NORTHWEST AREA; CURB WALL AT 6". OK TO GROUT.
09/08/2017 BUILDING - PROGRESS Partial Approval PLUMBING INTERMEDIATE: GAS VENT EXHAUST CHIMNEY SYSTEM: 7 RISERS AT 24", VENTS AT LEVEL #1 THROUGH ROOF AREA.
09/07/2017 BUILDING - PROGRESS Partial Approval STEM WALL: LEVEL #1; WEST ENTRY. OK TO PLACE GROUT.
FRAMING: ROOF LEVEL - WEST WALL AT GL: 1/A - F. OK TO COVER.
BUILDING PRE-SLAB: LEVEL #1, NORTH WEST STAIRWELL LANDING: OK TO PLACE CONCRETE.
SHEETROCK NAILING: LEVEL #2, GL: C/4.5 - 5 (ONE LAYER); NORTH SHAFT - WEST AND SOUTH WALLS (ONE LAYER)
09/01/2017 BUILDING - PROGRESS Partial Approval SHEETROCK NAILING: SECOND LAYER; LEVEL #1, GL: C/3 - 4; LEVEL #2; GL: 3/B - F; C/1 - 3.
FIRE CAULKING/FIRE STOP: NOT READY ON LEVEL #1 - OFFICE AND CONTROL ROOM WALLS.
08/31/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT AT GL: F/3 - 5 TOP-OUT: OK TO GROUT PROGRESS AREA.
08/30/2017 BUILDING - PROGRESS Partial Approval ELECTRIC INTERMEDIATE: LEVEL #1, GL: B/1 - 3; 3/B.5 - C IN WALL ROUGH-INS.
08/30/2017 BUILDING - PROGRESS Partial Approval SHEET ROCK NAILING lEVEL #1; OFFICE. OK TO TAPE. LEVEL #2, GL: 2.5'A - F (1 LAYER; C/1 - 3 (2 LAYERS. OK TO TAPE PROGRESS AREAS.
08/28/2017 BUILDING - PROGRESS Partial Approval SHEETROCK NAILING - LEVEL #2; GL: 2/B - F, TOP OUT AT 12' BELOW DECK ABOVE (TWO LAYERS). GL: C/2 - 3 (FIRST LAYER) BOTH SIDES OF WALL - OK TO TAPE PROGRESS AREAS.
08/25/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: EAST SIDE AT GL: 5/A - F; A/3 - 5; F/3 - 5. OK TO GROUT CMU WALLS (TOPPED OUT)
08/25/2017 BUILDING - PROGRESS Partial Approval FRAMING: LEVEL #1; GL: 1 - 2.5/B; 2.5/B - C. OK TO COVER.
08/25/2017 BUILDING - PROGRESS Partial Approval SHEET ROCK NAILING: LEVEL #1, TOP-OUT AT GL: 1 - 2.5/ (12'); IDF ROOM; CONTROL ROOM; ONE SIDE SHEETROCK.
08/24/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT GL: 1/C - F; F/1 - 3; SCREEN WALL AT NORTH WEST CORNER; TOP OUT. OK TO PLACE GROUT.

SHEETROCK NAILING: TOP-OUT AT 8' BELOW DECK ABOVE: GL: 2/B - F; (2 LAYERS); C/1 - 2 (1 LAYER) OK TO TAPE PROGRESS AREAS.

ELECTRIC INTERMEDIATE: LEVEL #2, WALL ROUGH-IN AT GL: 2/B - F; C/1 - 2.
08/23/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 36' - 40': GL: A/3 - 5; 5/A - F; F/3 - 5. OK TO GROUT PROGRESS AREAS.
08/21/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 36' - 40'; GL: 5/A - F; A/3 - 5; F/3 - 5. OK TO GROUT PROGRESS AREAS.
08/18/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 32' - 36' AT GL: A/3 - 5; 5/A - F; F/3 - 5. OK TO GROUT PROGRESS AREAS. SHEETROCK NAILING: LEVEL #2, GL" 2/B - F; SECOND LAYER TOP-OUT (8' - 11') TO DECK ABOVE. FIRST LAYER TOP-OUT AT GL: C/1 - 3; AT 8' TO 10'. OK TO TAPE PROGRESS AREAS.
08/16/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT; CMU WALLS AND SCREEN WALL (NW) AT 32' - 36'. GL: A/1 - 3; A - F/1; F/1 - 3. ENSURE ALL REBAR IS PROPERLY PLACED. OK TO GROUT PROGRESS AREAS.
08/14/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT ON CMU WALLS AT 28' - 32'; GL: 5/A - F; A/3.5 - 5; F/3.5 - 5. OK TO PLACE GROUT. SHEET ROCK NAILING: GL: 2/B - F; TOP - OUT AT 11' BELOW DECK ABOVE; FIRST LAYER OF 2 HOUR RATED CORRIDOR.
08/09/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 24' - 28': GL: 5/A - F; A/4 - 5, F/4 - 5. OK TO GROUT PROGRESS AREAS.
08/08/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT. CMU WALLS AT 24' TO 28'; GL: 1/A - F; F/1 - 2; A/1 - 2. OK TO GROUT PROGRESS AREAS.
08/07/2017 BUILDING - PROGRESS Partial Approval FRAMING: LEVEL #1; GL: A.5/2.5 - 3.5; LEVEL #2 GL: 2/B - F; D/1 - 2. SHEETROCK NAILING: LEVEL #1, GL: A.5/2.5 - 3.5; TOP - OUT AT 12 FEET BELOW DECK ABOVE. OK TO TAPE PROGRESS AREA.
08/03/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 20' - 24'; GL: A/4 - 5; 5/A - F; F/4 - 5. OK TO PLACE GROUT.
08/02/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 16' - 20'; GL: 1/A - F; F/1 - 2' A/1 - 2; OK TO GROUT PROGRESS AREAS.
07/31/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT; CMU WALLS AT 16' - 20'; GL: A/4 - 5; 5/A - B. CMU WALLS AT 12' - 15'; GL: A/1 - 1.5; 1/A - A.5. OK TO GROUT PROGRESS AREAS.
07/27/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT; CMU WALLS AT GL: A/4 - 5; 5/A - B AT 12' - 16'. CMU WALLS AT 16' - 20' AT GL: 5/B - F, F/4 - 5. OK TO GROUT PROGRESS AREAS.
07/26/2017 BUILDING - PROGRESS Partial Approval ROOF LEVEL; 6 PILASTERS; GL: 1/E - F; 2/E - F; 4/E - F: STEM WALL AT GL: E/1 - 5. OK TO POUR PROGRESS AREAS.
07/25/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT; CMU WALLS AT 12' - 16' AT GL: 5/B - F; F/4 - 5; F/1 - 2; 1/A - F, A/1 - 2. OK TO GROUT PROGRESS AREAS.
07/20/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 8' - 12', GL: 1/A-D; A/1 - 3. OK TO GROUT PROGRESS AREA.
07/18/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS AT 8' - 12': GL: 5/A - F; F/1 - 5; 1/D - F. OK TO GROUT PROGRESS AREAS.
07/10/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS (12" BLOCK) AT 4' - 8' AFFE; GL: 5/A-F, F/4 - 5. OK TO GROUT PROGRESS AREAS. COLUMN DOWELING IS NOT READY ON LEVEL 1.
07/06/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT - FIRST LIFT AT 0" - 48" A.F.F.E : GL: 1 -2/A, 1 A - F; 1/A - F; F/1 - 2. OK TO GROUT PROGRESS AREAS: MASONRY WALLW AT 0" - 48" AT GL: A/4 - 5' 5/A -F; F/3 -5 HAVE BEEN GROUTED.
06/27/2017 BUILDING - PROGRESS Not ready for Inspection ELECTRIC INTERMEDIATE - TEP VAULT (GROUND LEVEL) - CABINETS/PANELS AND GROUNDING SYSTEM BELOW ARE NOT READY: WILL BE RECALLED FOR 28 JUNE. COLUMN WRAPS NOT READY - ENGINEER REQUIRED ADDITIONAL REBAR TO BE ADDED (DRILLED AND EPOXIED).
06/26/2017 BUILDING - PROGRESS Not ready for Inspection LEVEL #3, SLAB ON METAL DECK: FOWELS FOR EQUIPMENT PADS NEED TO BE INSTALLED; SOUT WEST AREA; CHAIRS TO BE PLACE TO RAISE REBAR OFF THE DECKING; SEVERAL REBAR NEED TO BE SECURED. GENERAL CLEAN-UP. AREA FOREMAN (CONCRETE - PAT) TO CHECK STATUS AT THE END OF THE WORK DAY. IF NON-COMPLIANT - POUR MUST BE RESCHEDULED.
06/12/2017 BUILDING - PROGRESS Partial Approval ELECTRIC TEMP POWER - 200 AMP SERVICE (POWER POLE) - OK TO ENERGIZE. CODE: TMPP. ELECTRIC UNDERGROUND - PARTIAL: 5" CONDUIT LINES (STUB-UPS - SES): 6 POWER LINES; 1 COMMUNICATION LINE. OK TO COVER PROGRESS LINES.
06/07/2017 BUILDING - PROGRESS Partial Approval NINE STEEL COLUMNS DRY-PACKED; GL: 5/A - F (5), 3/A - D (3), F/4 (1)
05/12/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: MOISTER BARRIES AND REBAR ARE IN PLACE; ALL PIPING IS WRAPPED. OK TO PLACE CONCRETE.
04/17/2017 BUILDING - PROGRESS Partial Approval ELECTRIC UNDERGROUND: CHILLER PUMPS: 4 EACH 4" LINES AT GL: 1.5/C - D; HOT WATER: 3 EACH 1 1/4" LINES AT GL: B/3 - 3.5; CHILLED WATER PUMPS: 4 EACH LINES AT GL: D/3.75 - 4.5; IBF ROOM: 1 EACH 5" LINE; 2 EACH 1" LINES. FURTURE LINES 1 AT 4"; 1 EACH AT 2"; COMMUNICATIONS LINE: 1 AT 5" LINE.
04/06/2017 BUILDING - PROGRESS Partial Approval MASONRY PRE-GROUT: CMU WALLS (12" BLOCK) AT GL: 1/A - C; A/ 1 - 5; 5/A - C; WALLS AT 0" - 54". OK TO GROUT PROGRESS AREAS.
04/02/2017 BUILDING - PROGRESS Partial Approval INFORMATION - TESTING SET FOR 3 APRIL.
11/29/2016 BUILDING - PROGRESS Partial Approval 20" DIAMETER BORE AT APPROXIMATELY 75'.