| 04/23/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 04/23/2018 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 10/09/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
NORTH WEST STAIR AREA, GL: A/1 - 1.5; GAS METERING AREA GL: F.5/3 - 5. OK TO PLAC CONCRETE. |
| 07/31/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
LEVEL #3; 9 EACH PILASTERS AT GL: B/1 - 5; 1 - 5/B - D; STEM WALL AT GL: B/1 - 5; EDGE WALL AT GL: A/2.5 - 3. OK TO PLACE CONCRETE. |
| 07/24/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
LEVEL #3, PILASTERS - NOT READY FOR INSPECTION. WILL RESCHEDULE FOR 26 JULY. |
| 05/04/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
SIX EQUIPMENT PADS WITH #4 REBAR AT 12" ON CENTER; MOISTURE BARRIER IN PLACE. OK TO PLACE CONCRETE. |
| 03/28/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
GRADE BEAM AT GL: 1/B - F, F/1 - 3; BEAM NEEDS PROPER CLEARANCE ON WEST SIDE OF FOOTING, VERTICALS NEED TO BE PLACED AS PER PLANS. OK TO PLACE CONCRETE WHEN CORRECTIONS HAVE BEEN COMPLETED. |
| 03/23/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
GRADE BEAM FOOTING AT GL: F/3 - 5, B - F/5. NOTE: BULKHEAD FOR GRADE BEAM AS PER DETAIL #2, PAGE S0.4 |
| 03/16/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
GRADE BEAM #1 AT GL: 1/A - B; 5/A - B; GRADE BEAM #2 AT GL: A/1 - 5. OK TO PLACE CONCRETE. |
| 03/15/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
REBAR PLACEMENT IS INCOMPLETE. PLEASE RECALL WHEN REBAR IS IN PLACE AND FORMS ARE IN PLACE. |
| 03/14/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
NEED TO COMPLETE REBAR PACEMENT AND SET FORMS. NOTE: RFI SUBMITTED FOR GB1: OK TO STACK #10 REBAR AT 4 BARS AT EACH LEVEL WITH PLACEMENT 3" APART: 8 TOTAL BARS. GB2; STACK 2 LAYERS OF #11 BARS (5 EACH) LAYER AT 3" APART. |
| 03/08/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PIER CAPS (3) AT GL: 3/D; E/2; E/4. OK TO PLACE CONCRETE |
| 03/01/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
CAISSON FOOTINGS AND CAGES (5) AT GL: D/1, 3; A/3; .5A/1, 2. |
| 02/28/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
CAISSON FOOTINGS AND CAGES AT GL: B/3, 4; E/2, 4, 5. |
| 02/27/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
3 EACH CAISSON FOOTINGS AT GL: B/1; C/4; F/5; 2 EACH 44'4" CAGES. OK TO PLACE CONCRETE AND CAGES. |
| 02/24/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
3 EACH CAISSON FOOTINS AT A/3, A/5, B/5. CONCRETE AND CAGES TO BE PLACED. |
| 02/24/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
CAISSON FOOTINGS AND CAGES AT GL: F/1, 2, 4, 5. CONCRETE AND CAGES TO BE PLACED. CAGES AT 30' (2); 44'4" (3) |
| 02/22/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
CAISSON FOOTING CAGES - 5 EACH AT 4' X 30'. OK TO PLACE. |
| 01/24/2017 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
C.U.P. AREA (SW CORNER) STORM WATER DIVERTER WALL. OK TO POUR PROGRESS AREA. |