Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 04/25/2017 |
FRAMING |
|
Approved |
APPROVED |
| 04/21/2017 |
FRAMING |
|
Partial Approval |
complete collar ties at entry, and verify insulation. plumbing - provide clearance and support b-vent, complete t + p line, have gas iso approved with city oftucson. |
| 03/17/2017 |
FRAMING |
|
Not ready for Inspection |
expose fire place framing to verify clearance to unit and flue, verify gas sizing for w/heater s correct, and install w/heater to code, expose a small portion of roof framig in game room. have new electrical inspected and have electrician verfy on company letterhead its installed to code, ok to cover H.D. in game room, incomplete inspection. |