Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2017 | REINFORCED MASONRY PRE-GROUT | Approved | ||
| 06/14/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | UNIT 'C' SOUTH WALL OK TO 12'. B/C SOUTH HALF OK TO T.O.W. C SOUTH 1/2 OF WEST WALL OK TO 4' | |
| 06/13/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 'B/C' NORTH 1/2 OF WALL OK TO T.O.W. SOUTH 1/2 TO 12' 'C' WEST WALL NORTH 1/2 OK TO T.O.W. |
|
| 06/12/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | 'B/C' NORTH 1/2 OF WALL OK TO T.O.W. SOUTH 1/2 TO 12' 'C' WEST WALL NORTH 1/2 OK TO T.O.W. |
|
| 06/09/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | UNIT C NORTH WALL OK TO TOP, B/C AND C WEST WALLS NORTH 1/2 OK FROM 4' TO 12' AND B/C SOUTH 1/2 OK TO 4' | |
| 06/08/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | C/B WALL OK TO TOP, NORTH WALL OF B OK TO TOP | |
| 06/06/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | UNIT 'C' OK TO TOP OF WALL. C/B SEPERATION WALL OK FROM 4' TO 12' WITH CLEANOUTS. | |
| 06/05/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | UNIT "C" NORTH WALL AT 16' - 20' ; UNIT "B" NORTH WALL AT 12' - 16'; INTER WALL BETWEEN UNITS "B" AND "C" AT 48". OK TO GROUT PROGRESS AREAS. | |
| 06/02/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | NORTH WALL AT UNITS B - A AT 4' TO 12' (CLEAN OUTS TO BE INSTALLED). OK TO GROUT PROGRESS AREAS. | |
| 05/31/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OK TO GROUT TO 12' (EASTERN UNIT ONLY) | |
| 05/19/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OKAY TO GROUT TO 54' NORTH AND SOUTH WALLS. | |
| 05/18/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | OK TO GROUT TO 54" AFF (EAST 1/3 OF BUILDING) |