Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2017 | ELECTRIC - FINAL | Approved | ||
| 06/02/2017 | ELECTRIC - FINAL | Denied | warning: next not ready or fail = refee | |
| 06/01/2017 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999 * |
|
| 04/18/2017 | ELECTRIC - FINAL | Not ready for Inspection | see notes from 9/28, and update plans, this install not per plan. | |
| 04/14/2017 | ELECTRIC - FINAL | Not ready for Inspection | RE-CALL ELECTRIC FINAL WITH BUILDING FINAL AT COMPLETION OF SOLAR INSTALLATION. | |
| 12/30/2016 | ELECTRIC - FINAL | Denied | ||
| 10/25/2016 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 09/30/2016 | ELECTRIC - FINAL | Partial Approval | main breaker bussing good for 100amps only or provide paper workIVRS - Inspection :* | |
| 09/28/2016 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999 40amp breaker to big for 100amp service, sub.panel A missing on print * |
|
| 09/19/2016 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* |