Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
Permit Number - T16CM04943
Inspection Description - REINFORCED MASONRY PRE-GROUT
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/08/2018 | REINFORCED MASONRY PRE-GROUT | Approved | ||
03/16/2018 | REINFORCED MASONRY PRE-GROUT | Cancelled | IVRS - AP canceled | |
03/07/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | PATIO - PLANTER AREAS ARE TOPPED OUT - OK TO GROUT PROGRESS AREAS. | |
03/05/2018 | REINFORCED MASONRY PRE-GROUT | Cancelled | IVRS - AP canceled | |
03/02/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | ||
03/02/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | UPPER PLANT/PATIO AREAS; TOPPED-OUT; NORTH WEST AND WEST SIDE WALLS (TOPPED - OUT). PLANTER NEXT TO EXTERIOR STAIRWELL (TOPPED OUT). OK TO GROUT PROGRRESS AREAS. | |
02/23/2018 | REINFORCED MASONRY PRE-GROUT | Approved | SITE WALLS AND RETAINING WALLS AT NORTH SIDE (2ND LIFT), NORTHWEST WALL AT GL: 1 - 4, SITE WALL AT SOUTH WEST PORTION OF ANGEL BUILDING - SECOND LIFT. OK TO GROUT PROGRESS AREAS. | |
02/12/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | EAST AND NORTHEAST SITE/RETAINING WALL AT 0" - 60"; WEST AND NORTH WEST SITE WALLS AT 0" - 48". OK TO GROUT PROGRESS AREAS. | |
02/07/2018 | REINFORCED MASONRY PRE-GROUT | Partial Approval | CMU WALLS AT 0" TO 56" AT GL: H - D/0.5 - 4. OK JTO GROUT PROGRESS AREAS, | |
09/21/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | MAIN ENTRY SCREEN WALL TOPPED -OUT AT 18'. OK TO GROUT AND CAP. | |
09/20/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | SITE WALL (MAIN ENTRY) AT 8' - 12' AFFE. GL: .5A/3.5 - 6.75. OK TO GROUT. | |
09/18/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | WEST SIDE ENTRY AREA OK TO GROUT TO 8' | |
09/14/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | ENTRY AREA, RETAINING WALLS; STAIR/RAMP AREA; FIRST LIFT AT 40" - 48" . WEST WALL (SOUTH PORTION) AT GL: .5A/6.75, NEEDS TO BE RE-MORTARED (APPROXIMATELY 8') | |
06/07/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | MAIN ENTRY TO GARAGE AT GL: 1/B - C, AS PER NOTE #4, PAGE S2.1. OK TO PLACE GROUT. | |
05/12/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | ELEVATOR SHAFT TOPPED-OUT AT 27' 4". OK TO GROUT PROGRESS AREAS. | |
05/11/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | ELEVATOR SHAFT CMU WALLS AT 23' ABOVE FIRST FLOOR - OK TO GROUT PROGRRESS AREA. | |
05/10/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | CMU LIFT AT 16' ABOVE FIRST FLOOR (ELEVATOR SHAFT). OK TO GROUT PROGRESS AREAS. | |
05/09/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | ELEVATOR SHAFT AT 9' ABOVE FIRST FLOOR LEVEL. OK TO GROUT PROGRESS AREA. | |
04/13/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | CMU WALLS AT 10' TOP-OUT: GL: A/1 - 8, 8/A - C; D/1 -5, CMU WALL AT 8': GL: 5/E - G; G/5 - 6; ELEVATOR AREA AT 12'. OK TO GROUT PROGRESS AREAS. | |
04/10/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | CMU WALL AT 0' - 4' AT GL: 5/E - G; CMU WALLS AT 4' - 8' AT GL: A/1 - 4.5; 1/A - D; D/ 1 - 3. OK TO GROUT PROGRESS AREAS. | |
04/06/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | CMU WALLS AT 4' - 8'; GL: A/4 - 8; D/3 - 5; 8/A - D. CMU WALLS AT 8' - 10' TOP-OUT, GL: H/4 - 9; 8/C - E; 5/D - E. OK TO GROUT PROGRESS AREAS. | |
04/04/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | CMU WALLS AT 4' - 8' AT GL: 5/D -E; E/4 - 5; 8/C - E; H/4 -9. CMU WALLS AT 8' - 10' (TOP - OUT) GL: E/4 - 5; E/8 -9; 3.5/E - H; 8/C - E; 9/E - H; OK TO GROUT PROGRESS AREAS. | |
04/02/2017 | REINFORCED MASONRY PRE-GROUT | Partial Approval | CMU WALLS AT 4' - 8' AT GL: E/4 -5, 4/E - H; 9/E - H; E/9 - 8; WALLS AT 0" - 48" GL: H/4 - 5. OK TO GROUT PROGRESS AREAS. |