Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T16CM04943
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/21/2018 | EXCAVATION/LAYOUT REBAR & ZON | Approved | OK TO PLACE CONCRETE FOR SITE WALL FOOTINGS AT SPEEDWAY. | |
03/13/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS IN AREA BETWEEN FAMILY BUILDING AND KELSCH BUILDING - OK TO PLACE CONCRETE. | |
03/12/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | CONTRACTOR CANCELLED. WORK INCOMPLETE. | |
02/12/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISSON FOOTINGS FOR LIGHT POLES (4). OK TO PLACE CONCRETE. | |
02/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS FOR SITE WALL AT GL: .5A/1 - 2.5, E.5 -G/ 1. TIE FOOTINGS INTO ANGEL BUILDING. OK TO PLACE CONCRETE. | |
02/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SITE WALLS FOOTINGS AT NORTH AND NORTHWEST PORTIONS. OK TO PLACE CONCRETE. | |
01/29/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SITE WALL FOOTINGS: GL: 3.5/D.5 - H; E - H/3; 3.1/E - H. OK TO PLACE CONCRETE. | |
01/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | NOT READY FOR INSPECTION - CONGRACTOR CANCELLED. WILL RESCHEDULE FOR 29 JAN. | |
11/02/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WEST SIDE OF BUILDING: F-3 FOOTING AT GL: A/3 -4; AS PER DETAIL #117. | |
09/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ENTRY AREA FOOTINGS; RAMP FOOTINGS AT GL: .5A/2.6 - 6.75; AS PER DETAILS #112 AND 119; PAGES S3 AND S4. OK TO PLACE CONCRETE. | |
09/08/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | ENTRY AREA FOOTINGS ARE NOT READY FOR INSPECTION. | |
09/06/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | CONTRACTOR CANCELLED. | |
02/15/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CONTINUOUS FOOTING AT GL: 1/A - B. OK TO PLACE CONCRETE. | |
02/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - RI canceled | |
02/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CONTINUOUS FOOTINGS AT Gl; D/1.5 - 5; 8/A - B; A/1.25 - 8; ELEVATOR AREA AT 5 - 525/A - A.25; COLUMNS FOOTINGS: C7/F2 AT C/6; C6/F6 AT D.5/6; C9/F2 (2) AT 4/B - C; C9/F1 AT 3/B - C (2); C6/F1 (2) AT 2/B - C. OK TO PLACE CONCRETE FOR FOOTINGS AND COLUMNS. | |
02/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CONTINUOUS FOOTINGS AT GL: 5/D-E, E/4 - 5, 4/E - H; E/4 -5; 5/E - G; G/5-6; G - H/5.5; 6/G - H; H/6 - 9; 9/E - H; E/8 - 9; B - E/9. COLUMNS: C6/F (2); 8.4/F - G; C7/F2 (2); C5/F1 (1); C6/F1 (2); GL: 7/B - G; C6/F1 AT 6/B; C6/F1 C9/F1 AT 6/F - G. OK TO PLACE CONCRETE IN PROGRESS AREAS. |