Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2018 | BUILDING PRE-SLAB | Approved | ||
| 02/27/2018 | BUILDING PRE-SLAB | Partial Approval | UNITS G-1 AND G-2 TICKET BOOTHS ONLY | |
| 02/26/2018 | BUILDING PRE-SLAB | Not ready for Inspection | provide 3" clearence from steel to earth | |
| 02/12/2018 | BUILDING PRE-SLAB | Partial Approval | F2 FOOTER AT BUILDING B F5 FOOTER AT BUILDINGS A AND B |
|
| 02/09/2018 | BUILDING PRE-SLAB | Partial Approval | FOOTINGS AT SOUTH SIDE OF BLDG 'A' OK TO POUR | |
| 06/27/2017 | BUILDING PRE-SLAB | Partial Approval | B1 AND A1 OK TO POUR | |
| 06/26/2017 | BUILDING PRE-SLAB | Not ready for Inspection | work not complete, call for UFER |