Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/07/2016 | BUILDING - PROGRESS | Approved | IVRS - Inspection :* | |
| 10/27/2016 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 10/27/2016 | BUILDING - PROGRESS | Partial Approval | sheathing and lathe on north side ok | |
| 10/06/2016 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 08/24/2016 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 08/24/2016 | BUILDING - PROGRESS | Partial Approval | 1- sheathing along south wall ok 2- framing not complete, track not anchored. |