Inspection Status: Partial Approval
Inspection History: SITE - SEWER
| Date |
Description |
Inspector |
Results |
Comments |
| 08/08/2016 |
SITE - SEWER |
|
Partial Approval |
IVRS - Inspection :* |
| 08/08/2016 |
SITE - SEWER |
|
Partial Approval |
HCS CONNECTION TO 1ST JOINT STUB FOR FUTURE PASSED STORM SEWER |
| 08/04/2016 |
SITE - SEWER |
|
Partial Approval |
IVRS - Inspection :* |
| 08/04/2016 |
SITE - SEWER |
|
Partial Approval |
continued to end of system, still need air test and all completed docs., approvals, ect. |
| 08/02/2016 |
SITE - SEWER |
|
Partial Approval |
FROM NEW MAN HOLE TO FIRST Y HCS ONLY 6". |
| 08/01/2016 |
SITE - SEWER |
|
Partial Approval |
IVRS - Inspection :* |