| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/21/2016 | BUILDING - FINAL | Approved | ||
| 10/18/2016 | BUILDING - FINAL | Partial Approval | PANIC HARDWARE IS REQUIRED AT BOTH EXIT DOORS. AIR BALANCE REPORT OK. |
|
| 10/14/2016 | BUILDING - FINAL | Partial Approval | BACKFLOW CERT, CHLORINATION REPORT OK. NEED AIR BALANCE REPORT AND FIRE FINAL. |
|
| 10/07/2016 | BUILDING - FINAL | Partial Approval | CLAMP GAS LINES TO BLOCKS. TIGHTEN REGULATOR VENT AT 1 UNIT. PROVIDE AIR BALANCE REPORT, CHLORINATION, AND BACKFLOW CERT. PROVIDE ADA SIGNAGE. |
|
| 10/05/2016 | BUILDING - FINAL | Partial Approval | SEE ENGINEER FOR OSA CFM. SECURE GAS LINES ON ROOF. I.D. EQUIPMENT ON ROOF. PROVIDE AIR BALANCE REPORT. PROVIDE CHLORINATION REPORT. PROVIDE SIGNAGE AT ADA RESTROOMS. PROVIDE A BUSHING AT ELEC. CONNECTION TO EX. FAN AND EXTND CONDUIT. PROVIDE AN APPROVED GASKET AT EX. FAN. SUPPORT ELEC CONDUITS. PROVIDE FRESH AIR INTAKES. EXTEND REGULATOR VENTS 3' FROM A/C UNITS. OK TOCLEAR COMMERCIAL GAS. |