Permit: T16CM03364

Parcel: 12405051A


Addresses:

870 E UNIVERSITY BL


Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T16CM03364

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
06/30/2017 ENGINEERING - FINAL Approved
06/29/2017 ENGINEERING - FINAL Approved
11/23/2016 ENGINEERING - FINAL Denied WENT OUT TO THE SITE AND CHECKED THE HEIGHT OF THE RISE FROM LANDING TO LANDING. THE HEIGHT DIFFERENCE BETWEEN THE LANDINGS ON AVERAGE IS 28 TO 29 INCHES, NOTHING APPEARS TO EXCEED THE 30 INCH MAX. THE SITE IS STILL DENIED AT THIS TIME AND WILL BE LOOKED AT BY THE BUILDING FINAL INSPECTOR AND THE BUILDING OFFICIAL.
11/23/2016 ENGINEERING - FINAL Partial Approval
11/22/2016 ENGINEERING - FINAL Denied LOOKED OVER THE SITE, CURRENTLY THE CONTRACTORS ARE WORKING ON ALL AREAS AT THIS TIME, SO THIS SITE IS UNACCEPTABLE FOR A TEMPORARY CERTIFICATE OF OCCUPANCY. THE FOLLOWING AREAS HAVE BEEN CHECKED FOR COMPLIANCE FOR HANDICAP ACCESS AND DO NOT MEET THE SPECIFICATIONS AT THIS TIME. 1) PEDESTRIAN ACCESS ON THE NORTHSIDE OF THE BUILDING IS BEING BLOCKED DUE TO CONSTRUCTION IN ALL AREAS. 2) THE HANDICAP ACCESS IS ALLOWED ONLY THROUGH THE REAR OF THE SITE BY THE USE OF RAMPS ALONG THE EAST SIDE OF THE BUILDING FROM THE ONE HANDICAP PARKING SPACE. THE IST 15 FEET OF THE RAMP HEADING EAST TO THE FIRST LANDING HAS A RISE OF APPROXIMATELY 8.5% OR MORE AND CROSS SLOPES THAT EXCEED 2%. HEADING NORTH FROM THE FIRST LANDING THE RISE IS LESS THAN 8.33% IN THE RUNNING SLOPE, AND LESS THAN 2% CROSS SLOPES. THE RAMP APPEARS TO STAY WITHIN THE TOLERANCES FOR RUNNING SLOPE AND CROSS SLOPE PAST THE 3RD LANDING. BETWEEN THE THIRD LANDING AND THE UPPER DECK THE THE RUNNING SLOPE CHANGES IN THE LAST 10 PLUS FEET WHERE IT EXCEEDS A RISE THAT IS GREATER THAN 8.5% AND AS MUCH AS 10% AT VARIOUS LOCATIONS. 3) THE HANDRAIL ALONG THE WEST SIDE OF THE RAMP APPEARS TO BE WEAK IN THE ALLIGNMENT AND MAY NEED TO HAVE SOME TYPE OF STIFFENERS ADDED. THIS DETERMINATION WILL BE MADE BY THE BUILDING FINAL INSPECTOR OR THE BUILDING OFFICIAL.