Inspection History Details
Inspection Status: Partial Approval
Inspection History: SITE - SEWER
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2016 | SITE - SEWER | Partial Approval | PENDING FINAL ALL TESTING DONE AND APPROVED |
|
| 06/15/2016 | SITE - SEWER | Partial Approval | MANHOLES: 1, 1A, 3, 4, 6, AND 7 ALL TEST APPROVED. #2 AND 5 FAILED FIRST TEST. SECOND TEST APPROVED. |
|
| 06/14/2016 | SITE - SEWER | Partial Approval | SEWER MAINS FROM MANHOLES 5 TO 7, 5 TO 4, 4 TO 2, 3 TO 2, 2 TO 1 AND 1 TO 1A ALL PRESSURE TESTED AT 5 PSI FOR 10 MINUTES ALL APPROVED. ALL APPROVED. MANDRELL PULLED IN ALL PVC MAINS APPROVED. |
|
| 06/09/2016 | SITE - SEWER | Partial Approval | MANHOLES NUMBER 6 AND 7 POURED. ENCACEMENT FROM MH1 TO 1A AND TO END OF ENCACEMENT ALSO SERVICE NEAR 1A ALL OK TO COVER. |
|
| 06/08/2016 | SITE - SEWER | Partial Approval | MANHOLES 3 AND 5 POURED, SADDLES INSTALLED AND OK TO WRAP. | |
| 06/07/2016 | SITE - SEWER | Partial Approval | PIPE FROM 5 TO 6 OK TO COVER. MANHOLES # 1,1A,2,AND4 BASES POURED. |
|
| 06/06/2016 | SITE - SEWER | Partial Approval | SEWER FROM MANHOLE 4 TO 5, 2 TO 4, AND 5 TO 7 OK TO BACKFILL. | |
| 06/02/2016 | SITE - SEWER | Partial Approval | FROM MANHOLE 1 TO 1A, TO 2, AND 3 ALL OK TO BACKFILL. |