Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 03/02/2017 |
ENGINEERING - FINAL |
|
Approved |
|
| 02/28/2017 |
ENGINEERING - FINAL |
|
Partial Approval |
MET WITH A&S PAVING AND LOOKED OVER THE WEST HANDICAP PARKING SPACE FOR THIS SITE, THE WEST PARKING SPACE IS NOT IN COMPLIANCE FOR THE RUNNING AND CROSS SLOPES IN VARIOUS LOCATIONS. |
| 02/24/2017 |
ENGINEERING - FINAL |
|
Partial Approval |
THE CREW FROM A&S PAVING IS ON SITE REPLACING THE MATERIAL THAT WAS REMOVED EARLIER THIS WEEK. CURRENTLY THEY HAVE THE EAST PARKING SPACE AND THE ACCESS AISLE PAVED AND ARE WORKING ON ROLLING THESE LOCATIONS. THEY HAVE PLACED MATERIAL IN THE NORTHERN HALF OF THE WEST PARKING SPACE BUT HAVE RUN OUT OF MATERIAL AND ARE HAVING TO WAIT FOR ADDITIONAL ASPHALT. WE HAVE LOOKED AT THE RUNNING AND CROSS SLOPES OF THE AREAS AND THEY APPEAR TO BE WITHIN COMPLIANCE AT THIS TIME.I WILL COME BACK TO THIS SITE ONCE THE C ADVISE ME TUGH WITH THE COMPACTIONS SO THAT i CAN TAKE MY FINAL READINGS OF THE SLOPES. |
| 02/16/2017 |
ENGINEERING - FINAL |
|
Partial Approval |
MET ON SITE WITH THE CONTRACTOR AND LOOKED OVER THE HANDICAP PARKING LOCATED ON THE SOUTHSIDE OF THE SITE. THEY WILL COME UP WITH A SOLUTION AND MAKE THE NECESSARTY CHANGES FOR THE SITE, AND THEN WILL RESCHEDULE THIS INSPECTION. |
| 01/20/2017 |
ENGINEERING - FINAL |
|
Partial Approval |
ADA PARKING ON SOUTH SIDE INSTALLED . OK FOR TEMP C OF O PER ENGINEERING ONLY. |
| 01/19/2017 |
ENGINEERING - FINAL |
|
Continued |
MET WITH GC WALKED SITE WENT OVER WORK TO COMPLET FOR FINAL. |