Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date |
Description |
Inspector |
Results |
Comments |
| 04/05/2017 |
BUILDING PRE-SLAB |
|
Approved |
|
| 03/22/2017 |
BUILDING PRE-SLAB |
|
Partial Approval |
PORCH AREA ON SOUTH SIDE AND FIREPLACE FOOTER, ALONG WITH 1 COLUME FOOTER ON SOUTH SIDE. |
| 03/08/2017 |
BUILDING PRE-SLAB |
|
Partial Approval |
EAST END (BR 3 & 4, HALL, AND BATHROOMS) OK TO POUR |
| 02/15/2017 |
BUILDING PRE-SLAB |
|
Partial Approval |
LOWER FLOOR LEVEL EAST SIDE OK TO POUR |