| 01/30/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
ELECTRIC UNDERGROUND: 14 EACH 6" ELECTRICAL CONDUITS FOR THE DUCT BANK AT GL: 4/G.5 - H. OK TO PLACE CONCRETE. |
| 01/19/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
FRAMING - EXTERIOR FRAMING AT PENTHOUSE. OK TO COVER EXTERIOR WALLS. 2. ELECTRIC INTERMEDIATE - PARTIAL: EXTERIOR OUTLETS; INTERIOR OUTLETS AND SWITHCES - OK TO COVER. |
| 01/19/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
SHEET ROCK NAILING: EXTERIOR STAIRWELL #4 AT GL: 4.2/C.5 - D; C.5/3.5 - 4.2: LEVELS 5 - 10. OK TO WATER PROOF PROGRESS AREAS. |
| 01/12/2017 |
BUILDING - PROGRESS |
|
Partial Approval |
LEVEL 5; SLAB 5.5 - OK TO PLACE CONCRETE |
| 12/12/2016 |
BUILDING - PROGRESS |
|
Partial Approval |
GRADE BEAM AT GL: G/8 - 10. OK TO PLACE CONCRETE IN PROGRESS AREA. NORTH AND NORTHEAST FOOTINGS MISSING VERTICAL REBAR (NOT READY FOR INSPECTION) |
| 12/11/2016 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
STEM WALL MISSING REBAR |
| 12/07/2016 |
BUILDING - PROGRESS |
|
Partial Approval |
9.1 OK TO POIR, TRAUMA NOT READY |
| 11/29/2016 |
BUILDING - PROGRESS |
|
Partial Approval |
BUILDING PRE-SLAB AT LEVER #3.4. NEED TO CLEAN AND PLACE CHAIRS. OK TO PLACE CONCRETE WHEN COMPLETED. |
| 11/18/2016 |
BUILDING - PROGRESS |
|
Partial Approval |
2.4 LOWERED SLAB OK TO POUR |
| 11/16/2016 |
BUILDING - PROGRESS |
|
Not ready for Inspection |
#10 REBARS INCORRECTLY PLACED IN GRADE BEAM. |
| 11/15/2016 |
BUILDING - PROGRESS |
|
Partial Approval |
LEVEL #7; SLAB 7.1 AT GL; G - D/4,2 - 9. OK TO PLACE CONCRETE. |
| 11/03/2016 |
BUILDING - PROGRESS |
|
Partial Approval |
LEVEL #4: SLAB 4.3 (LOWER); GL: B.3/12 - 14.2; 14.2/ B.3 - F.75; 13 - 14.2/ F.75; 13/ F.75 - C.8; C.8/12 - 13. OK TO PLACE CONCRETE |
| 11/02/2016 |
BUILDING - PROGRESS |
|
Partial Approval |
SLAB ON GRADE ON LEVEL #4: 4.2 AT GL: 7.5 - 11, SLAB 4.3 TO BE COMPLETED ON 11-3-16. |
| 10/19/2016 |
BUILDING - PROGRESS |
|
Partial Approval |
ELECTRIC INTERMEDIATE - PARTIAL: EPU AT GL: 1.2 (WATER PUMP FOR UPPER LEVELS) OK TO ENERGIZE |