Permit: T16CM00577

Parcel: 12310001A


Addresses:

1501 N CAMPBELL AV

Inspection Status: Not ready for Inspection

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
04/12/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NOT READY - PLEASE RECALL WHEN READY.
04/05/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: 13/K - M; LOADING DOCK FOOTING AT GL: M/7 - 10.5. OK TO PLACE CONCRETE
04/04/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NOT READY - PLEASE RECALL FOR 5 APRIL
03/20/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STEM WALL AT STAIRWELL #3, GL: 4/M - N; 4.2/M - N; N/4 - 4.2. OK TO PLACE CONCRETE.
03/16/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTING AT GL: 4.1/M.1 - N. OK TO PLACE CONCRETE.
03/15/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NOT READY - PLEASE RECALL FOR 20 MARCH 2017
03/14/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANNOT DIG FOOTINGS UNTIL SCAFFOLDING IS MOVED.
03/13/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: 10/J - M. CLEAN OUT DEBRIS AND COMPLETE SETTING FORMS. OK TO POUR UPON COMPLETION OF CORRECTIONS.
03/08/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STEM WALLS AT GL: N/11 - 13; 10/N; (FIX) 4.2/ N - N.2; 7/B (PIER CAP). OK TO PLACE CONCRETE.
03/07/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection GRADE BEAM AT GL: 10/11, NOT READY. RECALL WHEN BEAM IS COMPLETE.
02/22/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: N/10 - 11; FORMS ARE IN PLACE. OK TO PLACE CONCRETE.
02/21/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NEED TO SET GRADE BEAM FORMS
02/08/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: 13/H - I. OK TO PLACE CONCRETE.
01/30/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: M; 23 EACH #4 REBARS TO E MOVED ON TO THE TOPSIDE OF THE #7 REBARS, NOT ATTACHED TO THE UNDERSIDE OF THE PARS. STAIRWELL #3 FOOTING NOT READY - REMOVING CONCRETE IN ORDER TO SET REBAR FOOTING.
01/24/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: 4.2/H - M. FINISH PLACING FORMS, OK TO PLACE CONCRETE
01/23/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection MISSING VERTICAL REBAR.
01/19/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection GRADE BEAM NOT READY.
01/09/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: H - I/10. OK TO PLACE CONCRETE. REQUESTED STEM WALL IS NOT READY FOR INSPECTION.
12/29/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STEM WALL FOOLTING : GL: G/12 - 14. OK TO PLACE CONCRETE.
12/05/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: D/5 - 6. OK TO PLACE CONCRETE
12/01/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STEM WALL FOOTINGS AT GL: B/9.5 - 10.5; 12/B - C; 12/C - C.25; 12 - 12.75/C; 12.75/B - C; 4.15/G - F. OK TO PLACE CONCRETE IN PROGRESS AREAS.
11/21/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAMS LINE 7 FROM D TO G AND LINE 4 FROM D TO E OK TO POUR
11/17/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STEM WALL/FOOTINGS AT GL: B/4.2 - 6; 4 - 4.2/C.75; 4/C.75 - D. OK TO PLACE CONCRETE.
11/16/2016 EXCAVATION/LAYOUT REBAR & ZON Prior to Final Inspectn STEM WALL AT NW PORTION OF BUILDING
11/16/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection STEM WALL IN NW PORTION OF BUILDING
11/08/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STEM WALL FOOTINGS AT GL: A.75/4.2 - 5.75; 4.15/B - C.4; 3.8/D.1 - B. DETAILS # 8/F3, 15B/F3. OK TO PLACE CONCRETE.
11/08/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STEM WALL FOOTINGS AT GL: 4.5/C.4;
11/01/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTINGS AT GL: B/5.5 -8.6. OK TO PLACE CONCRETE
10/30/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: D/8 - 10. OK TO PLACE CONCRETE
10/26/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection WILL RECALL FOR 27 0CT 16
10/24/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: D/5 - 6; CLEAN EAST END AREA OF EXCESS DIRT AND DEBRIS. OK TO PLACE CONCRETE
10/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL 5 (5.1) SLAB - OK TO PLACE CONCRETE.
10/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval
10/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAM AT GL: C.8/ 11.4 - 13.2. OK TO SET FORMS AND PLACE CONCRETE.
10/13/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection GRADE BEAM AT GL: D/5.5 - 6 NOT; RECALL WHEN READY FOR INSPECTION
10/12/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ELEVATOR PITS AT GL: C.8 - F.3/ 12.5 -13 (WEST WALL S AND EAST TOP - OUT WALLS) NORTH ELEVATOR (NORTH WALL) TO BE INCLUDED IN BOND BEAM. OK TO PLACE CONCRETE.
10/11/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NORTH ELEVATOR PIT (NORTH WALL)
10/10/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval NORTH WEST STAIR LANDING PAD; 3' X 9' - REBAR REENFORCED. OK TO POUR PROGRESS AREA.
10/07/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ELEVATOR WALLS (WEST) AT GL: C.75 - F.5/ 13; VERTICAL #4 REBAR RESET AND EPOXIED.
10/06/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection DEMO ELEVATOR PITS
10/04/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection ELEVATOR PITS IN THE PROCESS OF BEING DEMOLISHED.
08/05/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAMS AT GL: B.3/13 - 13.5; GRADE BEAM AT GL: K/13, L/13: TOP-OUT CAISSONS AT GL: H/13; H/13.6; N.3/ 9.7. OK TO POUR PROGRESS AREAS.
08/01/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISSON FOOTINGS (TOP-OUT) AT GL: A.9/10.5; B.3/14; B/9.5; B/10; C.3/10.5; C.2/13; C/5/13; C.3/10.5; E/11; F.3/11; G/11; H/11; H/13.6
07/28/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISSON FOOTINGS WITH CAGES: GL: H/13.6 (4'), H/13 (5'), H/12 94'), i/12 (4') OK TO POUR PROGRESS AREAS.
07/26/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISSON FOOTINGS (23 JULY) : SPECIAL INSPECTED. (4') GL: C.2/13, 14/B.3. 25 JULY: CAISSON FOOTINGS WITH CAGES (4') GL: C.5/13; 14/C.2, C.5, D.5, E.2, F.5
07/26/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval B-13-5; H-12,13,14; I-11,12 CAISONS AND CAGES OK. OK TO POUR PENDING SPECIAL INSPECTION REPORT.

CHANGED FROM AP TO PA TO FACILITATE LATER INSPECTIONS.
07/22/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN FOOTINGS WITH CAGES; GL: J/13 (5'), K/12 (4'), I/13 (5'). OK TO POUR PROGRESS AREAS.
07/22/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISSON FOOTINGS WITH CAGES AT GL:13/ I, J, K, L, M, N. (5') OK TO POUR PROGRESS AREAS.
07/21/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISSON FOOTINGS WITH CAGES (4') GL: 10/B, 10.5/C.3, 11/E, 11/F.3, 11/G. ELEVATOR PIT WALLS; GL C.8 - D.75/ 12.25 -13; E.2 - F.3/12.25 - 13. OK TO POUR PROGRESS AREAS.
07/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval caisson footings at G.L.'s n.3/11, 9.5/b, n/12, j/12, a.9/10.5, ok to pour progress area
07/15/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5' CAISSON FOOTINGS (CAGE IN) GL; N/11; 4' CAISSON FOOTING (CAGE IN) GL; M/12. OK TO POUR. ELEVATOR PIT AT GL: 12.5 - 13/ C.3 - D.8; 12.5 - 13/ E.2 - F.3 OK TO POUR PROGRESS AREAS.
07/13/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5' CAISSON FOOTINGS AT GL; 10/ J, K, H, I, M. OK TO POUR PROGRESS AREAS. CAISSON AT L/10 WILL REQUIRE A RFI - SLURRY ADDED TO COMPENSATE FOR CAVE-IN
07/12/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4' CAISSON COLUMNS (TOP OUT) GL; N/6, 7, 8, 9. 5' CAISSON COLUMNS FOOTINGS (CAGES) GL: 10/K, L, M, N. OK TO POUR PROGRESS AREAS.
07/06/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 COLUMNS AT GL: C3.8/ 11 - 12, #903A PLATE WITH 24' X
1 X 1 1/4 ANCHOR BOLTS
06/20/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ELEVATOR WALLS FOR PUBLIC ELEVATORS #1 - 2; STAFF ELEVATOR - FORMED AND OK TO POUR
06/17/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED - WILL RE-CALL FOR 20 JUNE
06/15/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES INSPECTED: 28 EACH AT 4' AND 11 AT 5'
06/10/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PUBLIC ELEVATOR (SOUTH) - REBAR PLACEMENT FOR WALLS - OK TO ST FORMS AND POUR.
06/09/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ELEVATOR SHAFT (PUBLIC) NORTH AND SOUTH STEEL PLACEMENT APPROVED.
06/07/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED INTO CAISSON FOOTINGS AT GL: M/8, M/9. ELEVATOR PAD #3 - OK TO POUR PROGRESS AREAS.
06/03/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PUBLIC ELEVATOR PITS (2): GL: E - F/11.4 - 13. CAGES PLACED IN TO CAISSON FOOTINGS GL: F.4/13; B.2/13; M/6 - 7; PLATES AND BOLTS: 913A AND 915A. OK TO POUR PROGRESS AREAS.
06/02/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval DRILLING RIG DOWN - NO CAISSON DRILLING UNTIL FURTHER NOTICE
06/01/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED IN CAISSON FOOINGS AT GL: L/4.2; M/5; M/6. PLATES AND BOLTS 909A AND 904A. OK TO POUR PROGRESS AREAS.
05/31/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED IN 5 CAISSON FOOTINGS: GL: L/5; M.1/3.8; L.3/3.8; N/4.2; N/5. PLATES AND BOLTS 910A AND 911A. CAGES INSPECTED: 6 CAGES; 3 @ 5' AND 3 @ 4'. OK TO POUR PROGRESS AREAS.
05/26/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CONTRACTOR CANCELLED ; CAISSON DRILLING SUSPEDED UNTIL FURTHER NOTICE
05/25/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGE INSPECTIONS ONLY; 3 CAGES AT 4'; 3 CAGES AT 5'. CAISSON DRILLING SUSPENDED UNTIL FURTHER NOTICE, ELEVATOR AREA, PROBLEM WITH POURED CAISSONS.
05/24/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED IN CAISSON FOOTINGS AT GL: 4' CAGES AT J/5, 6,7; K/5, K/6: 5' CAGES AT J/4.2, K/4.2. PLATES AND BOLTS: 909A. 914A. OK TO POUR PROGRESS AREAS.
05/24/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES IN PLACE IN CAISSON FOOTINGS AT GL: (ALL CAGES ARE 4'), K/7, 8, 9; L/6, 7, 8, 9. PLATES AND BOLTS 910A. OK TO POUR PROGRESS AREAS
05/23/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED INTO CAISSON FOOTINGS AT GL; E/12, F.3/12, I/9, J/8, J/9, (4' CAGES) H/4.2, I/4.2 (5' CAGES) PLATES AND BOLTS: 910A AND 914A. OK TO POUR PROGRRESS AREAS
05/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
05/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED IN CAISSON FOOTINGS: GL; G/5, G/6 (5'); I/6, I/7, I/8 (4'). CAGES INSPECTED I/5,6,7,8 (4'), G/5, 6 (5') OK TO POUR PROGRESS AREAS.
05/17/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED IN CAISSON FOOTINGS; 5' CAGES; 7/G, 8/G 4.2/G, 7/F: 4' CAGES H/8, H/9 - OK TO POUR PROGRESS AREAS, 913 - 913A BOLTS AND PLATES
05/16/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES IN CAISSON FOOTINGS AT GL; D/5, D/6, D/7 (5'), E/5 (4')
05/16/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES IN PLACE IN CAISSON FOOTINGS:GL: (5') D/10, G/9, G/10. (4') E/10, F/9, F/10. CAGES INSPECTED ON GROUND: F/7, F/10
05/12/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGE PLACED INTO CAISSON FOOTING AT GL: E/4.2 (5' X 45') OK TO POUR PROGRESS AREAS. BOLTS AND PLATES #913A. UN-TAGGED CAGES CONSTRUCTED: 3 @ 4', 1 @ 5'
05/11/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED IN CAISSON FOOTINGS: C/4.2 (4'), B/4.2 (5') OK TO POUR PROGRESS AREAS.
05/10/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED IN CAISSON FOOTINGS: 5' X 45' D/9, D/8; 4' X 45'; E/8, E/9. F/8. BOLTS AND PLATES ON CAISSON SITE; OK TO POUR PROGRESS AREAS.
05/09/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED IN CAISSON FOOTINGS: C.4/3,8, D.7/3.8 CAGES INSPECTED; 5' X 45' E/4, D/4.2 *SPECIAL INSPECTION ON CISSONS B.5/4.2, F/4.2
05/06/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAGES PLACED INTO CAISSON FOOTINGS: C-5, C-6, C-7, C-8, C-9 OK TO POUR PROGRESS AREAS. CAGES: B-10 (4' X 45'), E-4 (5' X 45')
05/05/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval (4 MAY) CAGES IN CAISSON FOOTINGS: D - 3.8, E - 3.8, F - 3.8 (POURED) 5 MAY: B - 6, B - 7, B - 8, B - 8.6, OK TO POUR SUBJECT CAGES INSPECTED PRIOR TO PLACEMENT INTO CAISSON FOOTINGS