Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/25/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | ||
| 08/19/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | This was called in for today. Nobody had any idea why this was called in. They were informed any more inspections like this would would result in additional reinspection fees. All UG has been approved. Only waiting for hydro and flush. | |
| 08/19/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | All UG approved. Still need hydro. | |
| 08/16/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | Need to see pics of risers before final approval. Risers #9,6,3. |
|
| 08/12/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | Following up on NS inspection. East end approved. OK to backfill. 3stubups and thrust blocks. Still need to visualize remaining stubups and thrust blocks for risers only. | |
| 08/09/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Denied | cancelled. not ready. | |
| 08/08/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | All C900 pipe and tracer tha is already in place with thrust blocks may be back filled. An c 900 still to be laid ( on the East permimeter) may be back filled if no thrust block is need. Still needs 200 lb test Any c900 still requiring thrust blocks ( at connection to the buildings at SE corner perimeter, etc) may NOT be back filled until thrust blocks poured and visually inspected by the fire department. Contractor accpets responsibility of back filling before the pressure test. |