Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/29/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | Hydro approved. Still need to flush both lines. Still need to change FDC's. See #4 in previous inspection. | |
| 02/25/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 1) Still needs hydro on both lines. 2) Still needs flush on both lines. 3) OK to bury both lines. 4) Need to change manifold/siamese FDC's. Currently stamped with "standpipe" lettering. Need to be stamped with "auto spkr" lettering. |
|
| 02/19/2016 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 1) UG approved on main fire line. Still needs hydro. Ok to backfill. 2) UG/hydro still needed on remote FDC section. Not yet installed. |