Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/11/2016 | FIRE SPKLR - OH PIPING & HYDRO | Approved | ||
| 07/19/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for OH/piping for 6th and 7th floors. 2. Need to add upright coverage on 6th floor Northside. 3. Ok to sheetrock everything except areas that need more coverage. |
|
| 07/12/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for OH/piping for 5th floor. | |
| 06/21/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for OH/piping for 2nd and 4th floor. | |
| 05/24/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | 1. Partial for OH/piping for 1st and 3rd floor. |