| 07/14/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
This project started under Jose Cazares, When I took it over Az Pipeline was switching over services. Robert lee was the foreman on site. The only issue was 4334 e 28th backfill had settled badly. Robert repaired the settling and there are no other issues. |
| 04/22/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Met with Robert lee 247-0171 from Az Pipeline, we discussed the schedule, and I informed him that with the size of the project we will do a final walkthrough together upon completion. The construction as of now is going according to spec. |