Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 07/14/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
work started under Jose Cazares. Work complete the first week of July 2016. All street crossing look good and alleys are clean and level |
| 07/14/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
There are numerous addressess for this permit |
| 04/22/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Gas line installation continuing |
| 01/15/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
did pre-con with gregg prado, expressed compaction standard 923 and the repair and replacement of sidewalk, and curb removal. |