Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 06/09/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Work complete. Final. No issues. |
| 06/02/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Final walk-through. 8' section of sidewalk needs expansion material behind curb. Saw Cut and install backer rod with epoxy. Also complete striping to TDOT specifications. |
| 04/27/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Met Oscar to look at final ADA ramp to be installed. Field conditions will not accommodate ADA ramp in plan location. Engineer to review. |
| 04/15/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Visit to check ramps. Told Super to clean up Eastbourne. Dirt from excavation in roadway. |
| 04/14/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Check ADA ramp forms on Broadway/Eastbourne. Pour early 4/15. |
| 04/13/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Checked curb forms on Broadway/Eastbourne |
| 04/01/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Received sketch for new pedestrian access on Eastbourne and Broadway. Neet to meet with Traffic Engineering in field to verify locations of signage and striping. |
| 03/07/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Met with Oscar to discuss putting pedestrian access through median on eastbourne. Chestnut Construction will submit sketch for approval. |
| 03/07/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
2:30pm Called Oscar to have barricades from Country Club Rd removed due to no work. |
| 03/02/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Meeting with Oscar to discuss curb removal along Country Club Rd, and ADA ramps on Broadway and Eastbourne. |