Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 11/11/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Final. No Issues. |
| 10/04/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Talked to Jesse. Permit Expired. Need to renew. Still have sidewalk and curb to finish. |
| 08/22/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Checked forms on SW and DW aprons on Lee. OK to pour 8/23 an AM. |
| 07/21/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Checked forms on two ADA ramps and sidewalk. Compaction on Apron and SW. Okay to pour Monday 7/18. |
| 07/21/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Site Visit. Inspected ADA slopes on pour from 7/18. Checks ok. |
| 07/15/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Checked forms on two ADA ramps and sidewalk. Compaction on Apron and SW. Okay to pour Monday 7/18. |
| 06/29/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Laid out 2 revised ramps on 3rd ave with Jon from GC concrete. |
| 06/29/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Informed Tortolita Valley Homes to renew permit befor proceeding with anymore ROW work. |
| 05/19/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
TEP J2 cabinet in wing of future ADA access ramp along 3rd Ave. Jesse to contact TEP to adjust location of J2 box prior to installation of ramp. |
| 04/11/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Curb for East and North entrances poured. |
| 04/06/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Check forms on driveway. Curb and header. Failed compaction. Recompact and check 4/6 |
| 02/18/2016 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Inspected WCR forms. Pour Friday. Discussed new concrete driveway. |
| 12/01/2015 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Check forms for sidewalk. OK |
| 11/16/2015 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Sidewalk failed inspection. Exceeds 2% cross slope. 375 linear feet. |
| 11/09/2015 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Meeting with Jesse P. Sidewalk under construction. |
| 10/30/2015 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
3rd Ave utility work done. |