Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 04/28/2015 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Job done, close permit. |
| 04/20/2015 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Driveway compaction good, pouring concrete driveway. |
| 04/13/2015 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
On site spoke to concrete contractor. Saw cutting curb & asphalt. |
| 04/08/2015 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Precon on site with general contractor and John Carson concrete. |