Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - MEDICAL GAS/TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/01/2016 | PLUMBING - MEDICAL GAS/TEST | Approved | IVRS - Inspection :* | |
| 03/30/2016 | PLUMBING - MEDICAL GAS/TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 03/29/2016 | PLUMBING - MEDICAL GAS/TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 03/22/2016 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* | |
| 03/16/2016 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | ||
| 03/15/2016 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | ||
| 03/03/2016 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* | |
| 03/02/2016 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | ONE INSTALLER WORKING ON NITROS. PURGE GAS AND O2 CENSOR CHECKED. | |
| 03/01/2016 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | I WENT OVER MANY OF THE REQUIREMENTS OF THE NFPA WITH PHILLIP, INSTALLER, AND EDDIE WITH RELIANCE. WE DISCUSSED THE IMPORTANCE AND REQUIREMENTS REGARDING CLEANING THE TUBE ENDS AND KEEPING THE TUBE CAPPED DURING AND AFTER INSTALLATION. INSTALLER REPLACING O2 LINE. | |
| 02/25/2016 | PLUMBING - MEDICAL GAS/TEST | Denied | PHYSICAL EXAMINATION OF FIRST 3 FITTINGS OF EACH SYSTEM ( 12 JOINTS) SHOW SOME FORM OF DEFECT; LESS THAN COMPLETE PENETRATION, PIPE ENDS LESS THAT COMPLETELY DEBURRED. I CAN NOT ACCEPT THIS SYSTEM AND REQUEST THAT ALL JOINTS BE REASSEMBLED WITH CITY OVERSIGHT. INSTALLER PIPE CERTIFICATION IS CURRENT HOWERVER THERE IS REASON TO QUESTION BRAZERS ABILITY. * |