| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/08/2017 | ENGINEERING - FINAL | Approved | To be consistent with approval in devpack | |
| 06/02/2017 | ENGINEERING - FINAL | Partial Approval | OK FOR THE TEMPORARY C OF O AT THIS TIME. FINAL WILL NOT BE GIVEN TILL THE FOLLOWING ITEMS HAVE BEEN COMPLETED AND REINSPECTED. 1) INSTALL ALL THE GATES AS SHOWN ON THE APPROVED PLANS. 2) REDIRECT THE ROOF DRAINAGE OFF OF THE SIDEWALK AT THE SOUTHEAST CORNER OF THE NEW BUILDING SO THAT IT DOES NOT AFFECT THE PEDESTRIAN ACCESS INTO THE BUILDING. 3) CORRECT THE TRIP HAZARD IN THE SIDEWALK AREA LOCATED AT THE SOUTHWEST CORNER OF THE NEW BUILDING. THIS WILL REQUIRE THE REMOVAL OF SOME OF THE EXISTING SIDEWALK AND REPOURING IT SO THAT IT ALLOWS ACCESS ALONG THE SOUTHSIDE OF THE NEW BUILDING. | |
| 05/30/2017 | ENGINEERING - FINAL | Not ready for Inspection | CALL FOR RE-INSPECTION | |
| 05/04/2017 | ENGINEERING - FINAL | Continued | AWAITNG APPROVAL FOR LANDSCAPING CHANGES | |
| 05/02/2017 | ENGINEERING - FINAL | Partial Approval | 1) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD ADDRESSING SITE CHANGES MADE. 2) COMPLETE LANDSCAPING. |
|
| 03/30/2017 | ENGINEERING - FINAL | Continued | INSPECTION CALLED OUT FOR A PROGRESS REPORT AND TO GO OVER CHANGES MADE TO THE SITE SEE PERMIT# DP13-0233 FOR INSPECTION RESULTS | |
| 03/06/2017 | ENGINEERING - FINAL | Denied | COMPLETE CONSTRUCTION, CALL FOR RE-INSPECTION |