Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T15CM05730
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2017 | ENGINEERING - FINAL | Approved | ||
12/07/2016 | ENGINEERING - FINAL | Partial Approval | INSTALL PER PAGE 15 OF 21 TREE PLANTING DETAIL #3 AND COMPLET INSTALL OF ALL LANDSCAPEING ON AP PLANS. PROVIDE STABILIZATION ON ALL DISTURBED SOIL . PROVIDE MONITORING REPORT. COMPLET INSTALL OF ALL BIKE PARKING. REMOVE ALL CONSTRUCTION EQUIPMENT FROM PARKING AREAS. | |
12/05/2016 | ENGINEERING - FINAL | Continued | ||
12/01/2016 | ENGINEERING - FINAL | Not ready for Inspection | ||
11/08/2016 | ENGINEERING - FINAL | Continued | ENGINEERING OK WITH TEMP C OF O FOR STOCKING ( ONLY). | |
11/01/2016 | ENGINEERING - FINAL | Continued | WALKED SITE WITH GC WENT OVER PARKING AREAS THAT ARE OVER 2%. AND WORK THAT NEEDS TO BE COMPLET FOR FINAL. | |
10/06/2016 | ENGINEERING - FINAL | Continued | ||
09/30/2016 | ENGINEERING - FINAL | Continued | GROUT FOR TRASH ENCLOUER OK. 2'6'' WALL ON NORTH SIDE OF SITE OK. LAST GROUT ON WALL ON SOUTH SIDE OF SITE | |
09/30/2016 | ENGINEERING - FINAL | Continued | ||
08/29/2016 | ENGINEERING - FINAL | Continued | INSPECTION PER HIGHLIGHS ON PAGE C3.30. | |
08/29/2016 | ENGINEERING - FINAL | Continued | MET WITH THE CONTRACTOR AND LOOKED AT THE FOLLOWING ITEMS FOR GROUT: 10 THE CMU WALL SOUTH OF THE FUTURE ROADWAY ALONG THE SOUTH SIDE OF THE PROJECT, LOCATED WEST OF THE CONSATRUCTION TRAILOR FOR APPROXIMATELY 100 FEET. 2) THE CMU WALLS FOR THE TRASH ENCLOSURE. BOTH OF THESE AREAS HAVE BEEN APPROVED FOR THE 1ST 4 FOOT LIFT OF THE WALLS. ALSO LOOKED AT THE STEEL FOR THE RETAINING WALL ALONG THE NORTHSIDE OF THE PROJECT SOUTH OF THE DRAINAGE CHANNEL BETWEEN INDIAN AGENCY ROAD AND THE EAST DRIVEWAY OFF OF VALENCIA, THIS AREA WILL BE POURED LATER TODAY. |
|
08/29/2016 | ENGINEERING - FINAL | Continued | CHECKED THE REBAR IN THE RETAINING WALL FOOTER ALONG THE SOUTHSIDE OF THE CHANNEL LOCATED AT THE NORTHEAST CORNER OF THIS SITE. THE CREW HAS BEEN CLEARED FOR THE POURING OF THE FOOTER | |
08/25/2016 | ENGINEERING - FINAL | Continued | INSPECTION PER HIGH LIGHTS ON PAGE C3.10. | |
08/22/2016 | ENGINEERING - FINAL | Continued | CCREEN WALL INSPECTION PER HIGH LIGHTS ON PAGE C3.10. | |
08/18/2016 | ENGINEERING - FINAL | Continued | PER HIGHT LIGHTS ON PAGE C3-10 . | |
08/17/2016 | ENGINEERING - FINAL | Continued | #4 REBAR IN SCREEN WALL 32'' ON C PER HIGH LIGHTS ON AP PLANS. | |
08/12/2016 | ENGINEERING - FINAL | Continued | REBAR FOR SCREEN WALL PER HIGH LIGHTS ON PAGE C2-2. | |
08/11/2016 | ENGINEERING - FINAL | Continued | ||
08/10/2016 | ENGINEERING - FINAL | Not ready for Inspection | ||
08/09/2016 | ENGINEERING - FINAL | Not ready for Inspection | ||
08/03/2016 | ENGINEERING - FINAL | Not ready for Inspection | ||
08/03/2016 | ENGINEERING - FINAL | Not ready for Inspection | ||
07/29/2016 | ENGINEERING - FINAL | Continued | SWPPP CONTROLS HAVE BEEN REPAIRED. | |
07/12/2016 | ENGINEERING - FINAL | Continued | MET WITH GC ABOUT SWPPP REPAIRS ON NORTH WEST SIDE OF SITE. KEEP A EYE ON TRACK OUT. | |
06/30/2016 | ENGINEERING - FINAL | Continued | NOTES ON DP15-0126. | |
06/27/2016 | ENGINEERING - FINAL | Continued | STORM WATER PIPING PER HIGH LIGHTS ON PLANS. | |
06/24/2016 | ENGINEERING - FINAL | Continued | NOTES ON ACTIVITY# DP15-0126 | |
06/23/2016 | ENGINEERING - FINAL | Continued | ||
06/22/2016 | ENGINEERING - FINAL | Continued | ||
06/20/2016 | ENGINEERING - FINAL | Continued | ||
06/20/2016 | ENGINEERING - FINAL | Partial Approval | CREWS ARE WORKING ON THE PLACEMENT OF REBAR FOR THE WALLS AND ROOF OF BOX CULVERT #1, IT IS APPROVED AT THIS TIME FOR THE PLACEMENT OF CONCRETE, THIS IS EXPECTED TO BE POURED TOMORROW MORNING. | |
06/14/2016 | ENGINEERING - FINAL | Not ready for Inspection | ||
06/14/2016 | ENGINEERING - FINAL | Continued | THE CREW IS TIEING THE STEEL FOR THE FOOTES AND THE FLOOR SLAB OF BOX CULVERT #1, THIS APPROVED AT THIS TIME FOR THE POURING OF THE CONCRETE. | |
06/13/2016 | ENGINEERING - FINAL | Continued | RETAINING WALL ON EAST SIDE OF SITE PER AP PLAN FOR REBAR. | |
06/06/2016 | ENGINEERING - FINAL | Continued | BOX CULVERTS HEAD WALLS / WING WALLS ON VALENCIA PER CULVERT DRAWING. | |
06/02/2016 | ENGINEERING - FINAL | Continued | RESCHEDULED FOR A LATER DATE | |
05/23/2016 | ENGINEERING - FINAL | Continued | ||
05/20/2016 | ENGINEERING - FINAL | Partial Approval | LOOKED OVER THE SITE TO SEE WHAT WORK IS HAPPENING AT THIS TIME. THE CREWS ARE CURRENTLY WORKING ON THE INSTALLATION OF THE REBAR FOR COR THE FOOTERS FOR THE CULVERTS #1 & #2 SOUTH VALENCIA FOR THE ROADWAYS INTO THE SITE. THEY ARE REMOVING ALL OF THE LOOSE MATERIAL FROM WITHIN THE FOOTER AREAS AND WILL BE READY FOR THE PLACEMENT OF CONCRETE LATER ON THIS MORNING. | |
05/18/2016 | ENGINEERING - FINAL | Continued | INSTALLED NEW ENTRANCE ON EAST SIDE OF SITE. WORKING ON BASIN PIPING ON NORTH SIDE OF SITE. | |
05/18/2016 | ENGINEERING - FINAL | Continued | ||
05/09/2016 | ENGINEERING - FINAL | Continued | NO SWPPP CONCERNS AT THIS TIME. | |
04/27/2016 | ENGINEERING - FINAL | Continued | WALKED SITE NO CONCERNS AT THIS TIME. | |
04/25/2016 | ENGINEERING - FINAL | Continued | REBAR FOR NORTH EAST BOX CULVER WING WALL INSTALLED. | |
04/25/2016 | ENGINEERING - FINAL | Not ready for Inspection | PAGE A-1 NEEDS TO BE COMPLE PER ZONING. | |
04/11/2016 | ENGINEERING - FINAL | Continued | 1) CREWS WORKING ON THE POURING OF CONCRETE FOR THE NORTHERN BOX CULVERT ON INDIAN AGENCY ROAD. 2) CREW WORKING ON INSTALLING THE WATER LINE AT THE NORTH WEST CORNER OF THE SITE BEHIND BIG O TIRE, THIS WORK IS BEING INSPECTED BY THE WATER DEPARTMENT. | |
04/07/2016 | ENGINEERING - FINAL | Continued | BOX CULVERTS REBAR INSTALLED PER DRAWING . | |
04/06/2016 | ENGINEERING - FINAL | Continued | HDPE STROM WATER PIPING PER HIGH LIGHTS ON AP APLANS. TALKED TO GC ABOUT PIPING COVER. | |
04/05/2016 | ENGINEERING - FINAL | Continued | NO CHANGES FROM LAST INSPECTION. | |
04/04/2016 | ENGINEERING - FINAL | Continued | TOP MAT ON BOX CULERT ON SOUTH EAST SIDE OF SITE PER DRAWINGS. HDPE STORM DRAIN PIPING PER HIGH LIGHTS ON AP PLANS. MET WITH GC ABOUT REPAIRS TO SWPPP CONTROLS ON WEST SIDE OF SITE. | |
04/01/2016 | ENGINEERING - FINAL | Continued | HDPE 24'' TO 18'' PER HIGH LIGHTS FOR STROM WATER ON AP PLANS. | |
03/30/2016 | ENGINEERING - FINAL | Continued | WORKING ON SOUTH WEST SIDE OF SOUTH BASIN. WORKING ON WALLS FOR BOX CULVERTS. WORKING ON PIPING NORTH WEST BASIN. |