Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/10/2017 | ENGINEERING - FINAL | Approved | ||
| 03/01/2017 | ENGINEERING - FINAL | Denied | SEE THE PREVIOUS COMMENTS FROM THE LAST INSPECTION OF THIS SITE, AND ENSURE THAT THIS SITE IS CONSTRUCTED PER THE APPROVED PLANS. ALSO THE DRIVEWAY INTO THE SITE DOES NOT MEET THE MAXIMUM CROSS SLOPE WITHIN THE SIDEWALK AREA. THIS AREA REQUIRES THAT THE SLOPE VALUES ARE 2% IN THE CROSS SLOPE, THIS AREA VARIES FROM 2.2 PERCENT TO 3.2 PERCENT. VERIFIED THAT THE PEDESTRIAN REFUGE AREAS DO NOT HAVE TO MEET THE REQUIREMENTS OF THE MAXIMUM CROSS SLOPE. THE PAKING SPACE AND ACCESS AISLE EXCEED THE 2% OF THE CROSS SLOPES, REPAIR THESE AREAS SO THAT THEY ARE LESS THAN 2%. |
|
| 11/01/2016 | ENGINEERING - FINAL | Denied | 1) INSTALL HC PARKING, REFUGE AREA, BIKE PARKING, BOLLARDS AND LANDSCAPING PER APPROVED PLANS. 2) COMPLETE SITE WORK, CALL FOR RE-INSPECTION |