Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/19/2019 | BUILDING - PROGRESS | Approved | (RVI) | |
| 07/23/2018 | BUILDING - PROGRESS | Partial Approval | ||
| 01/09/2018 | BUILDING - PROGRESS | Denied | NO ACCESS RECALL | |
| 10/27/2017 | BUILDING - PROGRESS | Partial Approval | cement board at main shower ok | |
| 10/03/2017 | BUILDING - PROGRESS | Partial Approval | INTERIOR OSB OK TO COVER RECALL SHOWER WALLS CEMENT BOARD |
|
| 10/02/2017 | BUILDING - PROGRESS | Not ready for Inspection | gates locked no access | |
| 10/06/2016 | BUILDING - PROGRESS | Partial Approval | ROOF OVERFRAME IS OK TO COVER. | |
| 09/22/2016 | BUILDING - PROGRESS | Partial Approval | ROOF NAILING OK, READY FOR ROOF OVER-LAY. RE-CALL WHEN 2X4'S ARE SECURED FOR ROOF OVERLAY. | |
| 09/06/2016 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 08/15/2016 | BUILDING - PROGRESS | Partial Approval | CONTRACTOR HAD QUESTIONS, REFERED HIM TO THE ARCITECT WHO DREW THE PLANS. | |
| 06/03/2016 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* NOT READY FOR INSPECTION | |
| 05/10/2016 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 05/09/2016 | BUILDING - PROGRESS | Not ready for Inspection | ||
| 09/29/2015 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* | |
| 09/17/2015 | BUILDING - PROGRESS | Partial Approval | STEM WALL OK TO POUR |