Permit: T15CM02281

Parcel: 117062000


Addresses:

151 E BROADWAY BL

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
08/17/2017 REINFORCED MASONRY PRE-GROUT Approved
08/30/2016 REINFORCED MASONRY PRE-GROUT Partial Approval LEVEL 3 CMU WALL AT 26' GL: 1/C - F; ELECTRIC AREA AT WEST ELEVATOR (SOUTH WALLS) LEVEL 1GL: G - G.5/ 1 - 4, 5 - 6; 6 - 7 ALL AT 8'8". LEVEL 1 (SOUTH WALL) AT 12' 8" AT GL: A.5/6 - 7, 4 -3. GROUT POCKETS AT LEVELS 3.5 - 4.5. OK TO GROUT PROGRRESS AREAS.
07/22/2016 REINFORCED MASONRY PRE-GROUT Partial Approval WEST RAMP CMU WALL AT 7' 4", RESTROOMS #404, NORTH WALL AT 56"; 304 TOP OUT, OK TO POUR PROGRESS AREAS.
07/21/2016 REINFORCED MASONRY PRE-GROUT Partial Approval WEST WALL RAMP WALL AT 16'; EAST RAMP WALL AT 17' 4", NORTH WALL AT COLUMN LINE (C - B) AT 21' 4", LINE A - C TOP OUT AT 21' 4"; NORTH WALL AT GL: 2 - 4 AT 21' 4". LEVEL 3: LOBBY BOILER ROOM #306 NORTH AND EAST WALLS AT 56'; MECHANICAL ROOM #304 AT 56'. OK TO GROUT PROGRESS AREAS.
07/14/2016 REINFORCED MASONRY PRE-GROUT Partial Approval WEST RAMP CMU WALL AT 12'8"; EAST RAMP WALL AT 21'8", ELECTRIC WALL AT 12'8", NORTH CMU WALL AT 21'8"
07/07/2016 REINFORCED MASONRY PRE-GROUT Not ready for Inspection FIRE MARSHALL SHUT DOWN JOB UNTIL STAIRS ARE PLACED IN ALL STAIRWELLS.
07/01/2016 REINFORCED MASONRY PRE-GROUT Partial Approval WEST RAMP WALL AT 16'8", NORTH WALL AT 12'8"; ELECTRIC ROOM NORTH WALL AT 7'8" - 10'; WEST WALL OF SE STAIRWELL AT 4'8"; SE STAIRWELL WEST WALL AT 4'8": OK TO GROUT PROGRESS AREAS.
06/15/2016 REINFORCED MASONRY PRE-GROUT Partial Approval ROOMS #111 AT 12'8"; 114 AT 10'; 134 EAST AT 12'8"; NORTH WALL AT GL: A.5/2.5 - 5. OK TO GROUT PROGRESS AREAS.
06/07/2016 REINFORCED MASONRY PRE-GROUT Partial Approval NORTH WALL AT LEVEL 1 AT 4'8"; RAMP WALL AT 8'8"; WALL AT ROOMS 136





LEVEL #1 NORTH WALLS AT 4'8"; RAMP WALL AT 8'8"; ROOMS #136, 137 (8'8"); 139; 141 (8'8"). *ROOM #139, DO NOT GROUT LINTEL AREA; AREA INSTALLED INCORRECTLY: MUST BE RE-SET
06/01/2016 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALLS AT 0" - 48" IN ROOMS #142 (NORTH WALL); 140; 139; 141; 136;; 137; 135; 133; 134 (WEST WALL). OK TO GROUT PROGRESS AREAS.
05/27/2016 REINFORCED MASONRY PRE-GROUT Partial Approval CMU WALL IN ELEVATOR #3 AT O" TO 56", AS PER NOTE #12 ON PAGE S2.0. OK TO GROUT PROGRESS AREA.
05/24/2016 REINFORCED MASONRY PRE-GROUT Not ready for Inspection NO REBAR PLACED IN MASONRY WALLS
03/24/2016 REINFORCED MASONRY PRE-GROUT Partial Approval GL A.8/3-4.5
03/11/2016 REINFORCED MASONRY PRE-GROUT Partial Approval
03/04/2016 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
03/03/2016 REINFORCED MASONRY PRE-GROUT Not ready for Inspection IVRS - Inspection :*