Permit: T15CM02281

Parcel: 117062000


Addresses:

151 E BROADWAY BL

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
08/17/2017 BUILDING PRE-SLAB Approved
07/06/2017 BUILDING PRE-SLAB Partial Approval FIRST POUR FOR CRANE-IN FILL AT 16" - LEVEL #1: 3500psi CONCRETE.
09/08/2016 BUILDING PRE-SLAB Partial Approval PUR BACK AT LEVEL #2.5 AT SOUTH EAST STAIRWELL; LEVEL #4.5: 8" BEAM (APPROXIMATELY 4') AT SE CORNER. OK TO POUR PROGRESS AREAS.
07/22/2016 BUILDING PRE-SLAB Partial Approval 2ND LEVEL AT SE CORNER: 10 CABLES REPLACED, SPECIAL INSPECTED. OK TO POUR BACK REPLACEMENT AREA.
07/14/2016 BUILDING PRE-SLAB Partial Approval CONTROL JOINTS AT LEVELS 3.5 - 4, 4 - 4.5. CLEAN OUT AREAS BEFORE POURING
07/01/2016 BUILDING PRE-SLAB Partial Approval LEVEL 6 - SLAB AT GL: A - G/ 5.5 - 8 - OK TO POUR PROGRESS AREA.
06/28/2016 BUILDING PRE-SLAB Partial Approval REBAR SYSTEM AT LEVEL 6, GL: 3.5 - 5.5/ A - G. OK TO POUR PROGRESS AREA.
06/01/2016 BUILDING PRE-SLAB Partial Approval POST TENSION SYSTEM AT LEVEL #5; GL: A - G/ 1 -4.5; COLUMNS AT B/6 - 7; C/7. OK TO POUR PROGRESS AREAS.
05/19/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
05/12/2016 BUILDING PRE-SLAB Partial Approval POST TENSION CABLE SYSTEM AT GL; 8/A - G; A/ 4.5 - 8; 4.5/A-G; G/1 - 4.5; 1/A-G; A/1-4.5. OK TO POUR PROGRESS AREA
05/05/2016 BUILDING PRE-SLAB Partial Approval GL 3.5-5.8/A-G 3RD TO 4TH FLOOR.
04/28/2016 BUILDING PRE-SLAB Partial Approval PT SLAB ON 3RD FLOOR GL 4.5/ A-G.
04/04/2016 BUILDING PRE-SLAB Partial Approval Ramp and 2nd floor Gl a-g/1-2.3 d-g/1-4
03/25/2016 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*