Permit: T15CM02281

Parcel: 117062000


Addresses:

151 E BROADWAY BL


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T15CM02281

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
08/17/2017 EXCAVATION/LAYOUT REBAR & ZON Approved
06/28/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5TH LEVEL COLUMNS D/4, D/5 - OK TO POUR. LEVEL 6 COLUMNS REQUIRING ADDITIONAL #5 REBAR:E/4, E/5, D/4, D/5, G/4, G/5, C/5
06/28/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN AT GL: F/6 - 3 #10 REBARS AND 3 RINGS ADDED. OK TO SET FORMS AND POUR
06/15/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ELEVATOR WALLS OF #1 AND #2 AT LEVEL 5.5. OK TO FORM AND POUR
06/15/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SE STAIRWELL AT LEVEL 5.5 - OK TO FORM AND POUR. 1/2 COLUMN AT GL: D/5 - OK TO FORM AND POUR
06/13/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS AT 5TH LEVEL GL: A/6; A/7; CONTROL JOINT AT SOUTH AREA BETWEEN LEVELS 1 & 2 - OK TO FORM COLUMNS AND POUR PROGRESS AREAS. NOTE: COLUMNS INSPECTED ON 10 JUNE 2016: A/8; B/8; C/7; C/8; E/5; E/6; E/7; F/5, F/7; F/8.
06/10/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5TH LEVEL 10 COLUMNS INSPECTED - OK TO SET FORMS AND POUR.
06/09/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN STEEL LEVEL 5 FOR DOLUMNS A4,B4,C4,D6,D7,D8,E8,G5,G6,G7,G8,B6,B7,A5,B4,C5 ALL OK
06/08/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL #5; COLUMNS AT GL: B/2; B/3; B/4; B/5 COLUMN TO BE CUT DOWN APPROXIMATELY 5 FEET. OK TO FORM AND POUR PROGRESS AREAS.
06/07/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 COLUMNS ON 5TH LEEL AT GL: D/3, E/1. OK TO SET FORMS AND POUR PROGRESS AREAS.
06/07/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PT SYSTEM ON LEVEL 5 - 5.5 - OK TO POUR. COLUMNS 3.5 / D5; SOUTHWEST STAIRWELL. OK TO POUR.
06/06/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL #5 - NORTH WEST STAIRWELL: COLOUMNS AT GL: A/1; B/1; C/1; D/1; F/1, F/2.3 (#7 REBAR DOWELS ADDED TO TOP OF COLUMNS) COLUMNS AT E/2.3; AND F/4 (5' OF COLUMNS TO BE REMOVED FROM DECK ABOVE). COLUMNS AT GL: A/3; B/3;, A/5; A/5; C/5 - #7 DOWELS ADDED TO COLUMNS. OK TO SET FORMS AND POUR PROGRESS AREAS.
06/03/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS ON 5TH LEVEL: GL: B/5, A/2; B/2; C/2. OK TO SET FRAMES AND POUR COLUMNS
05/31/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5TH LEVEL COLUMNS AT A/5 - 8; C/5. 2ND LEVEL PARAPET WALLS EAST (5 BAYS SE - NE) SOUTH - EAST FROM STAIRWELL TO CONSTRUCTION JOINT. OK TO FORM AND POUR PROGRESS AREAS.
05/26/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5TH LEVEL; 7 COLUMNS GL: B/8, C/8, D/6,7,8,. F/6, F/8: SOUTHEAST STAIRWELL, ELEVATOR #1 & 2. OK TO SET FORMS AND POUR PROGRESS AREAS
05/24/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4TH FLOOR COLUMNS AT GL: E/5, F/5, E/6, E/7, F/7, G/7, G/6, G/5, E/8, G/8. OK TO SET FORMS AND POUR PROGRESS AREAS
05/05/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3RD LEVEL REINFORCEMENT; 15 COLUMNS AT GL: C/6 - 8, 8/C - G, G/6 - 8; 6/D - G. OL TO SET FORMS AND POUR ROGRESS AREAS
05/02/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 18 columes 3rd to 4th floor GLa/6/1-4.
04/29/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection COLUMES INCOMPLETE.
04/26/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 6columes GL A/4-8,4/A-C 2nd to 3rd floor
04/25/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 11 COLUMES GL G-B/8 A.8/7, C-D, 6/A-C
04/22/2016 EXCAVATION/LAYOUT REBAR & ZON Approved 11 COLUMES GL D/6-7, E/5-7, FL5-7, G/5-7. 2ND TO 3RD FLOOR.
04/21/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
04/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/11/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Stairwell #2 2nd to 3rd floor
04/08/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection incomplete
04/07/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3 columes GL a-b/8
04/06/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2nd floor columes GL a-g/4, 3/a-g, 2-3/a-g
04/04/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Gl .8/a-b
03/24/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GL A.8/5-6
03/23/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 columes gl a.8/5-6
03/18/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/17/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/08/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/07/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/04/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/03/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
03/02/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/29/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/25/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/24/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/23/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/19/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/17/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/16/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/12/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/11/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/10/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/09/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
02/03/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/02/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
02/01/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
01/29/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
01/28/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 1ST LIFT ON ELEVATORS
01/27/2016 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
01/26/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
01/25/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
01/22/2016 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4 PEDESTALS AT CRANE AREA