Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T15CM01651
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/18/2015 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
12/10/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | INSPECTED RELOCATED FRONT ENTRY, OK TO COVER | |
09/29/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ||
08/24/2015 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | ||
08/24/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/24/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | DUMPSTER ENCLOSURES AND BOLLARDS | |
08/21/2015 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | ||
08/14/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/14/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PRE-GROUT ENTRY | |
08/12/2015 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | INSTALL TRASH ENCLOUSER PER AP PLANS. AND ADA OR PROVIDE REVSION. | |
08/04/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
08/04/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | INSTALLED PER UNAPPROVED REVISION PG 4 DP13-0075 | |
06/18/2015 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR COLUMN FOOTINGS |