Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 03/11/2021 |
BUILDING - FINAL |
|
Approved |
|
| 01/26/2021 |
BUILDING - FINAL |
|
Partial Approval |
PARTIAL - APPROVED FOR UNIT 8, 9, 11, 12 AND UNIT 10 NOT READY |
| 01/15/2020 |
BUILDING - FINAL |
|
Partial Approval |
Laundry building ok to drywall. |
| 04/13/2015 |
BUILDING - FINAL |
|
Prior to Final Inspectn |
Applicable for Units 1,2,3,4, and 5 only The northern 2 structures are in a FEMA SFHA and are required to have an elevation certificate returned to the ENG Section of PDSD. |