Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 05/27/2016 |
BUILDING - PROGRESS |
|
Approved |
IVRS - Inspection :* |
| 05/08/2015 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 04/17/2015 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 04/17/2015 |
BUILDING - PROGRESS |
|
Partial Approval |
TOP BEAM BOX ON WALL INSULATION OK |
| 04/09/2015 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 04/09/2015 |
BUILDING - PROGRESS |
|
Partial Approval |
OK TO PROCEED WITH STRAW BALES |
| 03/27/2015 |
BUILDING - PROGRESS |
|
Partial Approval |
IVRS - Inspection :* |
| 03/27/2015 |
BUILDING - PROGRESS |
|
Partial Approval |
OK TO GROUT STEM WALL |