Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/07/2016 | BUILDING - FINAL | Approved | IVRS - Inspection :* | |
| 10/14/2016 | BUILDING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999 1- SHALL PROVIDE BOUBLE WALL FLU VENT FOR THE WATER HEATER ALL THE WAY TO THE DRAFT COLLAR WHEN LOCATED IN AN EXTERIOR LOCATION. 2- SHALL CONNECT THE WASTE AND WATER TO THE KITCHEN SINK AND DISHWASHER. 3- SHALL PROVIDE A RECEPTICAL BOX FOR THE MICROWAVE OVEN. 4- SHALL PROVIDE A 50 AMP CIRCUIT FOR THE RANGE AS REQUESTED. * |
|
| 05/02/2016 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 04/27/2016 | BUILDING - FINAL | Not ready for Inspection | COMPLY W/ IRC CODE SECTIONS 105.8, 109.1.2, 2503.5.2, 2709.3, 2709.4, 2606.1, 2426.1, 2427.7.2. WINDOW SIL ELEVATION REMOVE ELECTRICAL CIRCUIT NOT SHOWN ON PLAN |
|
| 03/29/2016 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 02/25/2016 | BUILDING - FINAL | Denied | COMPLETE ALL REMAINING WORK SHOWN ON PLAN; IE. WATER HEATER WITH ENCLOSURE IS NOT YET INSTALLED, ALSO WATER HAMMER ARRESTORS, SEAL CLEANOUT PLUGS, SEAL WALL PENETRATIONS, REMOVE CONCRETE FROM GAS AND WATER RISERS, INSTALL ROOF FLASHING. EXPOSE A PORTION OF SHOWER PAN LINER TO SHOW COMPLIANCE WITH IRC 2709, CALL FOR INTERMEDIATE INSPECTION AS PREVIOUSLY REQUESTED. CORRECT WORK OR REVISE PLAN AS PREVIOUSLY REQUESTED. GAS TDL, RTU SIZING, STOVE 50 AMP CIRCUIT ALSO WINDOW HEADER DISCREPENCY. MISSING LIGHT ABOVE TOILET. PAY A REINSPECTION FEE FOR FAILING TO COMPLY WITH PREVIOUSLY NOTED CORRECTIONS. * |
|
| 01/28/2016 | BUILDING - FINAL | Not ready for Inspection | APPROVED PLANS ARE REQ FOR INSPECTION READ AND COMPLY WITH ALL PREVIOUSLY NOTED REQ COMPLETE ALL WK SHOWN ON PLANS |
|
| 06/01/2015 | BUILDING - FINAL | Not ready for Inspection | CLOSET FLANGE OK. ADD SUPPORT. GAS PLAN CHANGE REQUIRES PLAN REVISION | |
| 01/29/2015 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 01/29/2015 | BUILDING - FINAL | Not ready for Inspection | PLAN REVISION FOR PLUMBING LAYOUT & FIXTURES REQUIRED FOR FINAL | |
| 01/21/2015 | BUILDING - FINAL | Not ready for Inspection | IVRS - Inspection :* |