Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2016 | FIRE SPKLR - OH PIPING & HYDRO | Approved | followed up on inspector CC inspection. Hard lid already installed. Navarrete stated the work above ceiling was done. no head added in elevator shaft. state elev inspectors did not want. | |
| 02/01/2016 | FIRE SPKLR - OH PIPING & HYDRO | Partial Approval | -Elevator head still needs installation. -2 heads need to be added in south operating room to compensate for duct work placement -1 head to be added to Office/records room to compensate for dead space in between duct work. |
|
| 01/29/2016 | FIRE SPKLR - OH PIPING & HYDRO | Denied | Denied: 1st Floor: Head below elevator needs to be installed -2 heads in south "operating room" ( 2 furthest south heads) appear to be blocked by duct work -1 head in the north "operating room" (southeast head) is either missing or covered by the black foam - upright head in the "anesthesia room" is not there 2nd Floor -1 head in the "office/records" (northwest head) room appears to be blocked by the duct work -2 other heads in the "office/recirds" room (the 2 most southern heads) were either missing or unable to be seen - 1 head in the "mechaincal/equipment room" (second to last going south) looks to be sitting above the frame work. -1 upright in the hall outside the "Dr. Lounge" blocked by duct work The electrical/equipement room on the second floor was locked, I was unable to visualize the heads in that room. |