Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
Permit Number - T15BU00896
Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/19/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | ||
08/12/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Denied | 200 psi test was done on 77 feet of underground and passed, the last 7 to 8 feet for the riser section was cut out due possible leaking pressure from this section. OKAY to bury underground for safety but do not cover the last 7 to 8 feet away from the building for the riser, will need to do another 200 psi for 2 hours test again when connections are made to the riser. | |
08/10/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Denied | On site at 9:15 AM ask one underground contractor what time was the 200 pound pressure test started he state just about 1 hour ago, I went and looked at the pressure gauge and seen it's at 200 to 205 psi I did notice that the gauge was attached to a ¼ turn valve and two more ¼ turn valves on line making three altogether for this test. I sat by until 10:30 AM told the contractor that the 2 hours was up and the gauge still shows 200 - 205 psi. I then asked the contractor to find the handle for the ¼ turn valve just below the gauge (as it was missing) so that we can check and make sure the valve was open, we did find a handle and the valve was close when opening it the gauge went down to 50 PSI- TEST FAILED. Also called A-AAA and asked if the can resubmitted plans' showing what is on site the plans stated 6" C-900 pipe but its ductile iron piping was wrapped in plastic and has a tracer wire in place. Plans states restraint assembly clamps to be used but when I inspected they installed field lok 350 gasket joint restraints something I have not seen I asked the contractor to send in the paperwork and show that it's approved for fire lines. |
|
08/06/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Not ready for Inspection | Have not dug up the underground for inspection, but called us out for inspection. |