Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/17/2015 | FIRE SPKLR - FINAL | Approved | Flow switch passed test 40 seconds | |
| 08/28/2015 | FIRE SPKLR - FINAL | Partial Approval | Still need to perform test on flowswitch and tamper ( once it is installed) and verify signals to AZ Security Control ( monitoring co). 1. All valves controlling the water supply and all water flow shall be monitored. ( IFC 903.4). 2. Seperate permit for minitoring flow and tamper shall be pulled by the company permorming the installation (including work already performed). 3. Repair loose hanger in furnace closet. |