Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG PIPING FLUSH
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/15/2015 | FIRE SPKLR - UG PIPING FLUSH | Approved | Flushed all hydrants and risers stubs with a burlap sack all showed clean, also flushed the FDC's. | |
| 12/10/2015 | FIRE SPKLR - UG PIPING FLUSH | Partial Approval | Partial Approval Flushed hydrants: NE corner, All North side, all West side Flushed 1 riser on NE most side. Still need to complete South side and East side hydrant flushes and remaining stub ups ( x 9). |
|