Permit: T15BU00616

Parcel: 13323164A


Addresses:

7150 E SPEEDWAY BL


Inspection Status: Approved

Inspection History: FIRE SPKLR - FINAL

Permit Number - T15BU00616

Inspection Description - FIRE SPKLR - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
11/22/2016 FIRE SPKLR - FINAL Approved
04/14/2016 FIRE SPKLR - FINAL Partial Approval
04/07/2016 FIRE SPKLR - FINAL Denied PRESSURE TEST OKAY, BUT NO NFPA PAPERWORK, SPRINKLER HEADS WERE STILL TAPED AND THE ENTIRE EXISTING SYSTEM HAD BEEN TURNED OFF.
04/06/2016 FIRE SPKLR - FINAL Not ready for Inspection must hydro temporary supply to system 4 before final
03/24/2016 FIRE SPKLR - FINAL Cancelled Called phone # for applicant to see if the heads that were missing on the last OHPand H are installed. Contractor called back and said they were being installed now and wouldnt be done until this afternoon. Cancelled and they will call to reschedule final on system #4.
03/24/2016 FIRE SPKLR - FINAL Partial Approval heads over freezer still missing ( grid is not in yet). Was called out to determine if the dust wall between the occupied store and the 40,000 square feet to the West ( new area) can be taken down and a snow wall ( plastic netting) placed as a barrier to the public. Contractor needs to place drop ceiling and needs to remove the wall in order to do so. Systems in occupied parts of the building are fully functional per the contractor. System over area 4 is not connected, nor is the alarm system up yet. It was determined that the wall can be removed for the 24 hour construction to continue if
1. NO COMBUSTIBLES ARE TO BE BROUGHT INTO THE AREA OF WORK THAT IS NOT COVERED. METAL SHELVING MAY BE PLACED, BUT NOT STOCKED.
2. CONTINUOUS 24 HR FIRE WATCH TO BE IN PLACE UNTIL THE SPRINKLER SYSTEM COVERING NEW BUILD ( SYSTEM #4) HAS BEEN CONNECTED AND IS FUNCTIONING AND HAS PASSED ALL TESTS. RISER CAN NOT BE CONNECTED UNTIL AN UNDERGROUND FLUSH HAS BEEN PERFORMED.
09/03/2015 FIRE SPKLR - FINAL Partial Approval vision area only