Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/05/2015 | FIRE SPKLR - FINAL | Approved | ||
| 06/02/2015 | FIRE SPKLR - FINAL | Partial Approval | moved a branch line with five upright heads on it. ( lowered it for clearance from deck). Good work. However, the workers removed extra heads from over two bathrooms , a freezer, and a utility closet so construction crew could demo ceilings and replace them. Now they had to replace five heads. NS 6/2/15 |