Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
Permit Number - T15BU00427
Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/10/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | Hydrant tesed and flowed - passed | |
06/26/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | installed two missing valves for risers on East side. still need to flow hydrant # 7 |
|
06/22/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | 1. Flowed water from the following fire hydrants number 1-2-3-4-5-6 out of seven, #7 was not turned on to test still need to flow water from #7. 2. 200 PSI for 2 hours (Hydro) test completed for buildings number 2-3-12-13-14 & clubhouse lines were buried did not see placement - all passed pressure test. Buildings number 10 & 11 according to the contractor they did not have the isolation valves and were not installed according to the approved plans NOT APPROVED. 3. Need to keep the access roads on property clear of mud, pot holes, construction equipment and building supplies at all times 24 hours a day. 4. OKAY TO BUILD ANYWHERE ON PROPERTY. |
|
06/05/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | THE UNDERGROUND HYDRO HAD NOT BEEN DONE YET AND I HAD APPROVED THAT INSPECTION IN PERMITS PLUS ( JUST WENT BACK AND PUT IT IN AS A PARTIAL), SO THE CONTRACTOR CALLED IN A HYDRANT INSPECTION, BUT NEEDED THE HYDRO PRESSURE TEST FOR THE RISERS. UNDERGROUND WAS PRESSURIZED SINCE 7:30 AM 200 PSI - READ AT BASE OF FEED FOR RISERS FOR BUIDLINGS # 4,5,6,7,8,9 AND MAINTENANCE BUILDING ( 10:30 AM READ). THEY STILL NEED TO PRESSURIZE THE RISERS TO THE REMAINING BUILDINGS AND DO A FLUSH, BEFORE THE SPRINKLER OVERHEAD GOES IN . |
|
04/22/2015 | FIRE SPKLR - UG, PIPING, HYDRO | Partial Approval | CONTRACTOR ASKED IF THEY MAY BACKFILL BEFORE THEY PRESSURE TEST. LINES LAID FOR BUILIDNINGS #11, #10, #9, #8, #7, #6 AND #5 ARE APPROVED WITH THE EXCEPTION OF THE SOUTH EAST CORNER WHERE THERE IS AN ADDED FIRE LINE AND RISER NOT ON THE APPROVED PLANS ( FOR THE MAINTENANCE BUILDING). MAY NOT BACKFILL OVER THAT LINE UNTIL ASBUILDS ARE SUBMITTED TO FIRE FOR APPROVAL. NO HYDRO TEST PERFORMED YET NS |